Transcribers' Notes:
Some tables don't sum to the numbers indicated; no corrections have been made. All numbers are from the original.
Minor inconsistencies in hyphenation have been retained.

AMERICAN SOCIETY OF CIVIL ENGINEERS

INSTITUTED 1852


TRANSACTIONS


Paper No. 1155


THE NEW YORK TUNNEL EXTENSION OF THE PENNSYLVANIA RAILROAD.
THE NORTH RIVER TUNNELS. [A]

By B. H. M. Hewett and W. L. Brown, Members, Am. Soc. C. E.

[A] ]Presented at the meeting of June 1st, 1910.


Introduction.

The section of the Pennsylvania Railroad Tunnel work described in this paper is that lying between Tenth Avenue, New York City, and the large shaft built by the Company at Weehawken, N. J., and thus comprises the crossing of the North or Hudson River, the barrier which has stood for such a long time between the railroads and their possession of terminal stations in New York City. The general plan and section, [Plate XXVIII], shows the work included.

This paper is written from the point of view of those engaged by the Chief Engineer of the Railroad Company to look after the work of construction in the field. The history of the undertaking is not included, the various phases through which many of the designs and plans passed are not followed, nor are the considerations regarding foundations under the subaqueous portions of the tunnels and the various tests made in connection with this subject set out, as all these matters will be found in other papers on these tunnels.

This paper only aims to describe, as briefly as possible, the actual designs which were finally adopted, the actual conditions met on the ground, and the methods of construction adopted by the contractors.

For easy reference, and to keep the descriptions of work of a similar character together, the subject will be treated under the four main headings, viz.: Shafts, Plant, Land Tunnels, and River Tunnels.

Shafts.

It is not intended to give much length to the description of the Shafts or the Land Tunnels, as more interest will probably center in the River Tunnels.

The shafts did not form part of the regular tunnel contract, but were built under contract by the United Engineering and Contracting Company while the contract plans for the tunnel were being prepared. In this way, when the tunnel contracts were let, the contractor found the shafts ready, and he could get at his work at once.

Two shafts were provided, one on the New York side and one on the New Jersey side. Their exact situation is shown on [Plate XXVIII]. They were placed as near as possible to the point at which the disappearance of the rock from the tunnels made it necessary to start the shield-driven portion of the work.

The details of the shafts will now be described briefly.

The Manhattan Shaft.—The Manhattan Shaft is located about 100 ft. north of the tunnel center; there was nothing noticeable about its construction. General figures relating to both shafts are given in [Table 1.]

The Weehawken Shaft.—The Weehawken Shaft is shown in [Fig. 1]. This, as will be seen from [Table 1], was a comparatively large piece of work. The shaft is over the tunnels, and includes both of them. In the original design the wall of the shaft was intended to follow in plan the property line shown in [Fig. 2], and merely to extend down to the surface of the rock, which, as disclosed by the preliminary borings, was here about 15 ft. below the surface. However, as the excavation proceeded, it was found that this plan would not do, as the depth to the rock surface varied greatly, and was often much lower than expected; the rock itself, moreover, was very treacherous, the cause being that the line of junction between the triassic sandstone, which is here the country rock, and the intrusive trap of the Bergen Hill ridge, occurs about one-third of the length of the shaft from its western end, causing more or less disintegration of both kinds of rock. Therefore it was decided to line the shaft with concrete throughout its entire depth, the shape being changed to a rectangular plan, as shown in the drawings. At the same time that the shaft was excavated, a length of 40 ft. of tunnels at each end of it was taken out, also on account of the treacherous nature of the ground, thus avoiding risk of injury to the shaft when the tunnel contractors commenced work. There was much trouble with floods during the fall of 1903, and numerous heavy falls of ground occurred, in spite of extreme care and much heavy timbering. The greatest care was also taken in placing the concrete lining, and the framing to support the forms was carefully designed and of heavy construction; the forms were of first-class workmanship, and great care was taken to keep them true to line. A smooth surface was given to the concrete by placing a 3-in. layer of mortar at the front of the walls and tamping this dry facing mixture well down with the rest of the concrete. The east and west walls act as retaining walls, while those on the north and south are facing walls, and are tied to the rock with steel rods embedded and grouted into the rock and into the concrete. Ample drainage for water at the back of the wall was provided by upright, open-joint, vitrified drains at frequent intervals, with dry-laid stone drains leading to them from all wet spots in the ground. A general view of the finished work is shown in [Fig. 1], [Plate XXIX], and [Table 1] gives the most important dates and figures relating to this shaft.

TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1155.
HEWETT AND BROWN ON
PENNSYLVANIA R. R. TUNNELS: NORTH RIVER TUNNELS.

TABLE 1.— Particulars of Shafts on the North River Tunnels of the Pennsylvania Railroad Tunnels Into New York City.

Location. Depth, in feet. Width, in feet. Length, in feet. Excavation (including drifts) Concrete, in cubic yards. Date commenced. Date finished. Ground met: Lined with: Cost to Railroad Company. Cost per cubic foot.
Manhattan: 11th Avenue and 32d Street. 55 22 32 2,010 209 June 10th, 1903. December 11th, 1903. Top 13 ft. filled; red mica schist and granite. Concrete reinforced with steel beams down to rock. $12,943.75 $0.335
Weehawken: Baldwin Avenue. 76 At bottom 56, at top 100 At bottom 115.75, at top 154 55,315 9,810 June 11th, 1903. September 1st, 1904 Top 6 ft. filled, 30ft. sand hardpan, decomposed rock (trap and sandstone)below. Concrete with steel tie-rods in rock. 166,162,98 0.337

After the tunnel work was finished, both shafts were provided with stairs leading to the surface, a protective head-house was placed over the New York Shaft, and a reinforced concrete fence, 8 ft. high, was built around the Weehawken Shaft on the Company's property line, that is, following the outline of the shaft as originally designed.

Plant.

Working Sites.

Before beginning a description of the tunnel work, it may be well to set out in some detail the arrangements made on the surface for conducting the work underground.

All the work was carried on from two shafts, one at Eleventh Avenue and 32d Street, New York City—called the Manhattan Shaft—and one at Baldwin Avenue, Weehawken, N. J.—called the Weehawken Shaft.

The characteristics of the two sites were radically different, and called for different methods of handling the transportation problem. The shaft site at Manhattan is shown on [Plate XXX]. It will be seen that there was not much room, in fact, the site was too cramped for comfort; the total area, including the space occupied by the old foundry, used for power-houses, offices, etc., was about 3,250 sq. yd. This made it necessary to have two stages, one on the ground level for handling materials into the yard, and an overhead gantry on which the excavated materials were handled off the premises. The yard at Weehawken was much larger; it is also shown on [Plate XXX]. Its area was about 15,400 sq. yd. in the yard proper, and there was an additional space of about 750 sq. yd. alongside the wharf at the "North Slip," on the river front, connected with the main portion of the yard by an overhead trestle.

All the cars at Manhattan were moved by hand, but at Weehawken two electric locomotives with overhead transmission were used.

Power-House Plant.

At the Manhattan Shaft the power-house plant was installed on the ground floor of the old foundry building which occupied the north side of the leased area. This was a brick building, quite old, and in rather a tumble-down condition when the Company took possession, and in consequence it required quite a good deal of repair and strengthening work. The first floor of the building was used by the contractor as offices, men's quarters, doctor's offices, and so on, and on the next one above, which was the top floor, were the offices occupied by the Railroad Company's field engineering staff.

On the Weehawken side, the plant was housed in a wooden-frame, single-story structure, covered with corrugated iron. It was rectangular in plan, measuring 80 by 130 ft.

At both sides of the river the engines were bedded on solid concrete on a rock foundation.

The installation of the plant on the Manhattan side occupied from May, 1904, to April, 1905, and on the Weehawken side from September, 1904, to April, 1905. Air pressure was on the tunnels at the New York side on June 25th, 1905, and on the Weehawken side on the 29th of the same month.

The plants contained in the two power-houses were almost identical, there being only slight differences in the details of arrangement due to local conditions. A list of the main items of the plant at one power-house is shown in [Table 2].

TABLE 2.—Plant at One Power-House.

No. of itemsDescription of item.Cost.
Three500-h.p. water-tube Sterling boilers$15,186
TwoFeed pumps, George F. Blake Manufacturing Company740
OneHenry R. Worthington surface condenser6,539
TwoElectrically-driven circulating pumps on river front5,961
ThreeLow-pressure compressors, Ingersoll-Sergeant Drill Company33,780
OneHigh-pressure compressor, Ingersoll-Sergeant Drill Company6,665
ThreeHydraulic power pumps, George F. Blake Manufacturing Company3,075
TwoGeneral Electric Company's generators coupled to Ball and Wood engines7,626
Total cost of main items of plant$79,572
Sumary of Cost of One Plant.
Total cost of main items of plant$79,572
Cost of four shields (including installation, demolition, large additions and renewals, piping, pumps, etc.)103,560
Cost of piping, connections, drills, derricks, installation of offices and all miscellaneous plant101,818
Cost of installation, including preparation of site39,534
Total prime cost of one power-house plant$324,484

The following is a short description of each item of plant in [Table 2]:

Boilers.—At each shaft there were three 500-h.p., water-tube boilers, Class F (made by Sterling and Company, Chicago, Ill.). They had independent steel stacks, 54 in. in diameter and 100 ft. above grate level; each had 5,000 sq. ft. of heating surface and 116 sq. ft. of grate area. The firing was by hand, and there were shaking grates and four doors to each furnace. Under normal conditions of work, two boilers at each plant were able to supply all the steam required. The average working pressure of the steam was 135 lb. per sq. in.

The steam piping system was on the loop or by-pass plan. The diameter of the pipes varied from 14 in. in the main header to 10 in. in the body of the loop. The diameter of the exhaust steam main increased from 8 in. at the remote machines to 20 in., and then to 30 in., at the steam separator, which in turn was connected with the condensers. A pipe with an automatic relief valve from the exhaust to the atmosphere was used when the condensers were shut down. All piping was of the standard, flanged extra-heavy type, with bronze-seated gate-valves on the principal lines, and globe-valves on some of the auxiliary ones. There was an 8-in. water leg on the main header fitted with a Mason-Kelly trap, and other smaller water traps were set at suitable intervals.

PLATE XXIX.
TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1155.
HEWETT AND BROWN ON
PENNSYLVANIA R. R. TUNNELS: NORTH RIVER TUNNELS.

Each boiler was fitted with safety valves, and there were automatic release valves on the high-and low-pressure cylinders of each compressor, as well as on each air receiver.

Buckwheat coal was used, and was delivered to the bins on the Manhattan side by teams and on the Weehawken side by railroad cars or in barges, whence it was taken to the power-house by 2-ft. gauge cars. An average of 20 tons of coal in each 24 hours was used by each plant.

The water was taken directly from the public service supply main. The daily quantity used was approximately 4,000 gal. for boiler purposes and 4,400 gal. for general plant use. Wooden overhead tanks having a capacity of 14,000 gal. at each plant served as a 12-hour emergency supply.

Feed Pumps.—There were two feed pumps at each plant. They had a capacity of 700 cu. ft. per min., free discharge. The plungers were double, of 6-in. diameter, and 10-in. stroke, the steam cylinders were of 10-in. diameter and 10-in. stroke. An injector of the "Metropolitan Double-Tube" type, with a capacity of 700 cu. ft. per min., was fitted to each boiler for use in emergencies.

The feed-water heater was a "No. 9 Cochrane," guaranteed to heat 45,000 lb. of water per hour, and had a total capacity of 85.7 cu. ft. It was heated by the exhaust steam from the non-condensing auxiliary plant.

Condenser Plant.—There were two surface condensers at each plant. Each had a cooling surface sufficient to condense 22,500 lb. of steam per hour, with water at a temperature of 70° Fahr. and barometer at 30 in., maintaining a vacuum of 26 in. in the condenser. Each was fitted with a Blake, horizontal, direct-acting, vacuum pump.

Circulating-Water Pumps.—Two circulating-water pumps, supplying salt water directly from the Hudson River, were placed on the wharf. They were 8-in. centrifugal pumps, each driven by a 36-h.p., General Electric Company's direct-current motor (220 volts and 610 rev. per min.), the current being supplied from the contractor's power-house generators. The pumps were run alternately 24 hours each at a time. Those on the Manhattan side were 1,300 ft. from the power-house, and delivered their water through a 16-in. pipe; those on the Weehawken side were 450 ft. away, and delivered through a 14-in. pipe. There was also a direct connection with the city mains, in case of an accident to the salt-water pumps.

Low-Pressure Compressors.—At each plant there were three low-pressure compressors. These were for the supply of compressed air to the working chambers of the subaqueous shield-driven tunnels. They were also used on occasions to supply compressed air to the cylinders of the high-pressure compressors, thus largely increasing the capacity of the latter when hard pressed by an unusual call on account of heavy drilling work in the rock tunnels. They were of a new design, of duplex Corliss type, having cross-compound steam cylinders, designed to operate condensing, but capable of working non-condensing; the air cylinders were simple duplex. The steam cylinder valves were of the Corliss release type, with vacuum dash-pots. The valves in the air cylinders were mechanically-operated piston valves, with end inlet and discharge. The engines used steam at 135 lb. pressure. The high-and low-pressure steam cylinders were 14 in. and 30 in. in diameter, respectively, with a stroke of 36 in. and a maximum speed of 135 rev. per min. The two air cylinders were 23½ in. in diameter, and had a combined capacity of 35.1 cu. ft. of free air per revolution, and, when running at 125 rev. per min., each machine had an actual capacity of 4,389 cu. ft. of free air per min., or 263,340 cu. ft. per hour. The air cylinders were covered by water-jackets through which salt water from the circulating pumps flowed. A gauge pressure of 50 lb. of air could be obtained.

Each compressor was fitted with an automatic speed and air-pressure regulator, designed to vary the cut-off according to the volume of air required, and was provided with an after-cooler fitted with tinned-brass tube and eight Tobin-bronze tube-plates having 809 sq. ft. of cooling surface; each one was capable of reducing the temperature of the air delivered by it to within 10° Fahr. of the temperature of the cooling water when its compressor was operated at its fullest capacity. From the after-cooler the air passed into a vertical receiver, 4 ft. 6 in. in diameter and 12 ft. high, there being one such receiver for each compressor. The receivers were tested to a pressure of 100 lb. per sq. in. The after-coolers were provided with traps to collect precipitated moisture and oil. The coolers and receivers were fitted with safety valves set to blow off at 1 lb. above the working pressure. The air supply was taken from without, and above the power-house roof, but in very cold weather it could be taken from within doors.

PLATE XXX.
TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1155.
HEWETT AND BROWN ON
PENNSYLVANIA R. R. TUNNELS: NORTH RIVER TUNNELS.

High-Pressure Compressors.—There was one high-pressure compressor at each plant. Each consisted of two duplex air cylinders fitted to a cross-compound, Corliss-Bass, steam engine. The two steam cylinders were 14 and 26 in. in diameter, respectively, and the air cylinders were 14¼ in. in diameter and had a 36-in. stroke. The air cylinder was water-jacketed with salt water supplied from the circulating water pumps.

The capacity was about 1,100 cu. ft. of free air per min. when running at 85 rev. per min. and using intake air at normal pressure, but, when receiving air from the low-pressure compressors at a pressure of 30 lb. per sq. in., the capacity was 3,305 cu. ft. of free air per min.; receiving air at 50 lb. per sq. in., the capacity would have been 4,847 cu. ft. of free air per min. This latter arrangement, however, called for more air than the low-pressure compressors could deliver. With the low-pressure compressor running at 125 rev. per min. (its maximum speed), it could furnish enough air at 43.8 lb. per sq. in. to supply the high-pressure compressor running at 85 rev. per min. (its maximum speed); and, with the high-pressure compressor delivering compressed air at 150 lb., the combined capacity of the arrangement would have been 4,389 cu. ft. of free air per min.

The air passed through a receiver, 4 ft. 6 in. in diameter and 12 ft. high, tested under a water pressure of 225 lb. per sq. in., before being sent through the distributing pipes.

Hydraulic Power Pumps.—At each power-house there were three hydraulic power pumps to operate the tunneling shields. One pump was used for each tunnel, leaving the third as a stand-by. The duplex steam cylinders were 15 in. in diameter, with a 10-in. stroke; the duplex water rams were 2⅛ in. in diameter with a 10-in. stroke. The pumps were designed to work up to 6,000 lb. per sq. in., but the usual working pressure was about 4,500 lb. The piping, which was extra heavy hydraulic, was connected by heavy cast-steel screw coup lings having a hexagonal cross-section in the middle to enable tightening to be done with a bolt wrench. The piping was designed to withstand a pressure of 5,500 lb. per sq. in.

Electric Generators.—At each plant there were two electric generators supplying direct current for both lighting and power, at 240 volts, through a two-wire system of mains. They were of Type M-P, Class 6, 100 kw., 400 amperes, 250 rev. per min., 240 volts no load and 250 volts full load. They were connected direct to 10 by 20 by 14-in., center-crank, tandem-compound, engines of 150 h.p. at 250 rev. per min. A switch-board, with all the necessary fuses, switches, and meters, was provided at each plant.

Lubrication.—In the lubricating system three distinct systems were used, each requiring its own special grade of oil.

The journals and bearings were lubricated with ordinary engine oil by a gravity system; the oil after use passed through a "White Star" filter, and was pumped into a tank about 15 ft. above the engine-room floor.

The low-pressure air cylinders were lubricated with "High Test" oil, having a flash point of 600° Fahr. The oil was forced from a receiving tank into an elevated tank by high-pressure air. When the tank was full the high-pressure air was turned off and the low-pressure air was turned on, in this way the air pressure in the oil tank equalled that in the air cylinder being lubricated, thus allowing a perfect gravity system to exist.

The steam cylinders and the high-pressure air cylinders were fed with oil from hand-fed automatic lubricators made by the Detroit Lubrication Company, Detroit, Mich.

"Steam Cylinder" oil was used for the steam cylinders and "High Test" oil (the same as used for the low-pressure air cylinders) for the high-pressure air cylinders. The air cylinder and steam cylinder lubricators were of the same kind, except that no condensers were necessary. The steam cylinder and engine oil was caught on drip pans, and, after being filtered, was used again as engine oil in the bearings. The oil from the air cylinders was not saved, nor was that from the steam cylinders caught at the separator.

Cost of Operating the Power-House Plants.—In order to give an idea of the general cost of running these plants, [Tables 3] and [4] are given as typical of the force employed and the general supplies needed for a 24-hour run of one plant. [Table 3] gives a typical run during the period of driving the shields, and [Table 4] is typical of the period of concrete construction. In the latter case the tunnels were under normal air pressure. Before the junction of the shields, both plants were running continuously; after the junction, but while the tunnels were still under compressed air, only one power-house plant was operated.

TABLE 3.—Cost of Operating One Power-House for 24 Hours During Excavation and Metal Lining.

No.Labor.Rate per day.Amount.
6Engineers$3.00$18.00
6Firemen2.5015.00
2Oilers2.004.00
2Laborers2.004.00
4Pumpmen2.7511.00
2Electricians3.507.00
1Helper3.003.00
Total per day$62.00
Total for 30 days$1,860.00
Supplies.
Coal (14 tons per day)$3.25$45.50
Water7.007.00
Oil (4 gal. per day)0.502.00
Waste (4 lb. per day)0.070.28
Other supplies1.001.00
Total per day$55.78
Total for 30 days$1,673.00
Total cost of labor and supplies for 30 days$3,533.00

Stone-Crusher Plant.—A short description of the stone-crusher plant will be given, as it played an important part in the economy of the concrete work. In order to provide crushed stone for the concrete, the contractor bought (from the contractor who built the Bergen Hill Tunnels) the pile of trap rock excavated from these tunnels, which had been dumped on the piece of waste ground to the north of Baldwin Avenue, Weehawken, N. J.

The general layout of the plant is shown on [Plate XXX]. It consisted of a No. 6 and a No. 8 Austin crusher, driven by an Amex, single-cylinder, horizontal, steam engine of 120 h.p., and was capable of crushing about 225 cu. yd. of stone per 10-hour day. The crushers and conveyors were driven from a countershaft, in turn driven from the engine by an 18-in. belt.

TABLE 4.—Cost of Operating the One Plant for 24 Hours During Concrete Lining.

No.Labor.Rate per day.Amount.
2Engineers$3.00$6.00
2Firemen2.505.00
2Pumpmen3.006.00
1Foreman Electrician6.006.00
1Electrician3.003.00
1Laborer2.002.00
Total per day$28.00
Total for 30 days$840.00
Supplies.
Coal (14 tons per day)$3.15$44.10
Oil (4 gal. per day)0.502.00
Water13.0013.00
Other supplies2.002.00
Total per day$61.10
Total for 30 days$1,833.00
Total cost of labor and supplies for 30 days$2,673.00

The process of crushing was as follows: The stone from the pile was loaded by hand into scale-boxes which were lifted by two derricks into the chute above the No. 6 crusher. One derrick had a 34-ft. mast and a 56-ft. boom, and was worked by a Lidgerwood steam hoister; the other had a 23-ft. mast and a 45-ft. boom, and was worked by a "General Electric" hoist. All the stone passed first through the No. 6 crusher, after which it was lifted by a bucket conveyor to a screen, placed about 60 ft. higher than and above the stone bin. The screen was a steel chute pierced by 2½-in. circular holes, and was on a slope of about 45°; in order to prevent the screen from choking, it was necessary to have two men continually scraping the stone over it with hoes. All the stone passing the screen was discharged into a bin below with a capacity of about 220 cu. yd. The stone not passing the screen passed down a diagonal chute to a No. 8 crusher, from which, after crushing, it was carried back by a second bucket conveyor to the bin, into which it was dumped without passing a screen. The No. 8 crusher was arranged so that it could, when necessary, receive stone direct from the stone pile. The cars in which the stone was removed could be run under the bin and filled by opening a sliding door in the bottom of the bin. A track was laid from the bin to connect with the contractor's surface railway in the Weehawken Shaft yard, and on this track the stone could be transported either to the Weehawken Shaft direct, for use on that side of the river, or to the wharf, where it could be dumped into scows for transportation to New York.

The cars used were 3-cu. yd. side-dump, with flap-doors, and were hauled by two steam Dinky locomotives.

The average force employed was:

1foreman@$3.00perday. Supervising.
24laborers"1.75""Loading scale-boxes for derricks.
4laborers"1.75""Feeding crushers.
2laborers"1.75""Watching screens to prevent clogging.
1engineer"4.00""Driving steam engine.
2engineers"3.50""On the derricks.
1night watchman.Watching the plant at night.

Owing to the constant break-down of machinery, chutes, etc., inseparable from stone-crushing work, there was always at work a repair gang consisting of either three carpenters or three machinists, according to the nature of the break-down.

The approximate cost of the plant was:

Machinery $5,850
Lumber 3,305
Erection labor 3,999
————
Total $13,154

The cost of the crushed stone at Weehawken amounted to about $0.91 per cu. yd., and was made up as follows:

Cost of stone $0.22
Labor in operation of plant 0.31
Plant supplies 0.11
[B] Plant depreciation 0.27
———
Total $0.91

[B]Assuming that the scrap value of derricks and engines is one-half the cost, crushers one-third the cost, and other items nothing.

The crushed stone at the Manhattan Shaft cost about $1.04 per cu. yd., the difference of $0.13 from the Weehawken cost being made up of the cost of transfer across the river, $0.08, and transport from the dock to the shaft, $0.05.

Miscellaneous Plant.—The various pieces of plant used directly in the construction work, such as derricks, hauling engines, pumps, concrete mixers, and forms, will be found described or at least mentioned in connection with the methods used in construction.

The tunneling shields, however, will be described now, as much of the explanation of the shield-driven work will not be clear unless preceded by a good idea of their design.

Tunneling Shields.

During the period in which the original contract drawings were being made, namely, in the latter part of 1903 and the early part of 1904, considerable attention was given to working out detailed studies for a type of shield which would be suitable for dealing with the various kinds of ground through which the shield-driven tunnels had to pass. This was done in order that, when the contract was let, the engineer's ideas of the requirements of the shields should be thoroughly crystallized, and so that the contractor might take advantage of this long-thought-out design, instead of being under the necessity of placing a hurried order for a piece of plant on which so much of the safety as well as of the speed of his work depended. Eventually, the contractor took over these designs as they stood, with certain minor modifications, and the shields as built and worked gave entire satisfaction. The chief points held in view were ample strength, easy access to the working face combined with ease and quickness of closing the diaphragm, and general simplicity. A clear idea of the main features of the design can be gathered from [Fig. 3] and [Plate XXXI].

PLATE XXXI.
TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1155.
HEWETT AND BROWN ON
PENNSYLVANIA R. R. TUNNELS: NORTH RIVER TUNNELS.

The interior diameter of the skin was 2 in. greater than the external diameter of the metal lining of the tunnel, which was 23 ft. The skin was made up of three thicknesses of steel plate, a ¾-in. plate outside and inside, with a ⅝-in. plate between; thus the external diameter of the skin was 23 ft. 6¼ in. The length over all (exclusive of the hood, to be described later) was 15 ft. 11-7/16 in. The maximum overlap of the skin over the erected metal lining was 6 ft. 4½ in., and the minimum overlap, 2 ft.

There were no inside or outside cover-plates, the joints of the various pieces of skin plates being butt-joints covered by the overlap of adjoining plates. All riveting was flush, both inside and outside. The whole circumference of each skin plate was made up of eight pieces, each of which extended the entire length of the shield, the only circumferential joint on the outside being at the junction of the removable cutting edge (or of the hood when the latter was in position) with the shield proper.

Forward of the back ends of the jacks, the shield was stiffened by an annular girder supporting the skin, and in the space between the stiffeners of which were set the 24 propelling rams used to shove the shield ahead by pressure exerted on the last erected ring of metal lining, as shown on [Plate XXXI].

To assist in taking the thrust of these rams, gusset-plates were placed against the end of each ram cylinder, and were carried forward to form level brackets supporting the cast-steel cutting-edge segments. The stiffening gussets, between which were placed the rams, were also carried forward as level brackets, for the same purpose. The cast-steel segmental cutting edge was attached to the front of the last mentioned plates.

The interior structural framing consisted of two floors and three vertical partitions, giving nine openings or pockets for access to the face; these pockets were 2 ft. 7 in. wide, the height varying from 2 ft. 2 in. to 3 ft. 4 in., according to their location. The openings were provided with pivoted segmental doors, which were adopted because they could be shut without having to displace any ground which might be flowing into the tunnel, and while open their own weight tended to close them, being held from doing so by a simple catch.

For passing through the varied assortment of ground before entering on the true sub-river silt, it was decided to adopt the forward detachable extension, or hood, which has so often proved its worth in ground needing timber for its support, as shown in [Fig. 2, Plate XXIX]. This hood extended 2 ft. 1 in. beyond the cutting edge, and from the top down to the level of the upper platform. Additional pieces were provided by which the hood might have been brought down as far as the lower platform, but they were not used. Special trapezoidal steel castings formed the junction between the hood and the cutting edge. The hood was in nine sections, built up of two ¾-in. and one ⅝-in. skin plates, as in the main body of the skin, and was supported by bracket plates attached to the forward ends of the ram chambers. The hoods were bolted in place, and were removed and replaced by regular cutting-edge steel castings after the shields had passed the river lines.

The floors of the two platforms, of which there were eight, formed by the division of the platforms by the upright framing, could be extended forward 2 ft. 9 in. in front of the cutting edge, or 8 in. in front of the hood. This motion was given by hydraulic jacks. The sliding platform could hold a load of 7,900 lb. per sq. ft., which was equal to the maximum head of ground and water combined. The uses of these platforms will be described under the heading "Construction." The weight of the structural portion of each shield was about 135 tons.

The remainder of the shield was the hydraulic part, which provided its motive force and gave the power to the segment erector. The hydraulic fittings weighed about 58 tons per shield, so that the total weight of each shield was about 193 tons. The hydraulic apparatus was designed for a maximum pressure of 5,000 lb. per sq. in., a minimum pressure of 2,000 lb., and a test pressure of 6,000 lb. The actual average pressure used was about 3,500 lb. per sq. in.

There were 24 shoving rams, with a diameter of 8½ in. and stroke of 38 in. The main ram was single-acting. The packings could be tightened up from the outside without removing the ram, a thing which is of the greatest convenience, and cannot be done with the differential plunger type. Some of the chief figures relating to the shield rams, with a water pressure of 5,000 lb. per sq. in., are:

Forward force of one ram 275,000 lb.
Forward force of 24 rams (all) 6,600,000 lb.
Forward force of 24 rams 3,300 tons of 2,000 lb.
Equivalent pressure per square inch of face 105 lb.
Equivalent pressure per square foot of face 15,200 lb.
Pull-back force of one ram 26,400 lb.
Pull-back pressure on full area of ram 480 lb. per sq. in.

The rams developed a tendency to bend, under the severe test of shoving the shield all closed, or nearly so, through the river silt, and it is probable that it would have been better to make the pistons 10 in. in diameter instead of 8½ in.

Each sliding platform was actuated by two single-acting rams, 3½ in. in diameter and having a stroke of 2 ft. 9 in. The rams were attached to the rear face of the shield diaphragm inside the box floors, and the cylinders were movable, sliding freely on bearings in the floor. The front ends of the cylinders were fixed to the front ends of the sliding platforms. The cylinder thus supported the front end of the sliding platform, and was designed to carry its half of the load on the platform. Some of the leading figures in connection with the platform rams, at a working pressure of 5,000 lb. per sq. in., are:

Forward force of each pair of rams (in each platform) 96,000 lb.
Total area of nose of sliding platform 1,060 sq. in.
Maximum reaction per square inch on nose 90 lb.
Maximum reaction per square foot on nose 13,040 lb.

Each shield was fitted with a single erector mounted on the rear of the diaphragm. The erector consisted of a box-shaped frame mounted on a central shaft revolving on bearings attached to the shield. Inside of this frame there was a differential hydraulic plunger, 4 in. and 3 in. in diameter and of 48-in. stroke. To the plunger head were attached two channels sliding inside the box frame, and to the projecting ends of these the grip was attached. At the opposite end of the box frame a counterweight was attached which balanced about 700 lb. of the tunnel segment at 11 ft. radius.

The erector was revolved by two single-acting rams fixed horizontally to the back of the shield above the erector pivot through double chains and chain wheels keyed to the erector shaft.

The principal figures connected with the erector, assuming a water pressure of 5,000 lb. per sq. in., are:

Weight of heaviest tunnel segment 2,584 lb.
Weight of erector plunger and grip 616 lb.
Total weight to be handled by the erector ram 3,200 lb.
Total force in erector ram moving from center of shield 35,000 lb.
Total force in erector ram moving toward center of shield 27,500 lb.
Weight at 11-ft. radius which is balanced by counterweight 700 lb.
Maximum net weight at 11-ft. radius to be handled by turning rams 1,884 lb.
Total force of each rotating ram, at 5,000 lb. per sq. in. 80,000 lb.
Load at 11-ft. radius, equivalent to above 3,780 lb.

When the shield was designed, a grip was also designed by which the erector could handle segments without any special lugs being cast on them. A bolt was passed through two opposite bolt holes in the circumferential flanges of a plate. The grip jaws closed over this bolt and locked themselves. The projecting fixed ends of the grip were for taking the direct thrust on the grip caused by the erector ram when placing a segment.

It happened, however, that there was delay in delivering these grips, and, when the shield was ready to start, and the grip was not forthcoming, Mr. Patrick Fitzgerald, the Contractor's Superintendent, overcame this trouble by having another grip made.

In this design, also, a self-catching bolt is placed through the segment and the grip catches the bolt. In simplicity and effectiveness in working, this new design eventually proved a decided advance on the original one, and, as a result, all the shields were fitted with the new grip, and the original design was discarded.

The great drawback to the original grip was that the plate swung on the lifting bolt, and thus brought a great strain on the bolt when held rigidly at right angles to the erector arm. The original design was able to handle both Aand Bsegments, and key segments, without alteration; in the new design, an auxiliary head had to be swung into position to handle the key, but this objection did not amount to a practical drawback.

The operating floor from which the shield was controlled, and at which the valves were situated, was placed above the rams which rotate the erector, and formed a protection for them. The control of the shield rams was divided into four groups: the seven lower rams constituted one group, the upper five, another, and the six remaining on each side, the other two. Each group was controlled by its own stop and release valve. Individual rams were controlled by stop-cocks.

The control of the sliding platform rams was divided into two groups, of which all the rams on the upper floor made one, and all those in the lower floor, the other; here, again, each group had its own stop and release valve, and individual platforms were controlled by stop-cocks arranged in blocks from which the pipes were carried to the rams.

The in-and-out movements of the erector ram were controlled by a two-spindle, balanced, stop and release valve, controlled by a hand-wheel. The erector rotating rams were controlled by a similar valve, with four spindles, also operated by a single hand-wheel. Both wheels were placed inside the top shield pockets, and within easy reach of the operating platform.

The hydraulic pressure was brought through the tunnel by a 2-in. hydraulic pipe. Connection with the shield was made by a flexible copper pipe, the 2-in. line being extended as the shield advanced.

Land Tunnels.

General.

The following is a brief account of the main features of the "Land Tunnel" work, by which is meant all the part of the structure built without using tunneling shields.

The Land Tunnels consist of about 977 ft. of double tunnel on the New York side and 230 ft. on the New Jersey side, or a total of 1,207 lin. ft. of double tunnel.

The general design of the cross-section consists of a semi-circular arch, vertical side-walls and a flat invert. The tunnel is adapted for two lines of track, each being contained in its compartment or tunnel. The span of the arch is wider than is absolutely necessary to take the rolling stock, and the extra space is utilized by the provision of a sidewalk or "bench" forming by its upper surface a gangway, out of the way of traffic, for persons walking in the tunnels, and embedded in its mass are a number of vitrified earthenware ducts, for high-and low-tension electric cables. The provision of this bench enables its vertical wall to be brought much nearer to the side of the rolling stock than is usually possible, thus minimizing the effects of a derailment or other accident. Refuge niches for trackmen, and ladders to the top of the bench are provided at frequent intervals. In cases where a narrow street limits the width of the structure, as on the New York side, the two tunnels are separated by a medial wall of masonry, thus involving excavation over the entire width of both tunnels, and in such case the tunnels are spoken of as "Twin Tunnels"; where the exigencies of width are not so severe, the two tunnels are entirely distinct, and are separated by a wall of rock. This type is found on the Weehawken side. The arches are of brick, the remainder of the tunnel lining being of concrete.

New York Land Tunnels.

The work on the Land Tunnels on the Manhattan side was carried on from the shaft at 11th Avenue and 32d Street.

The plans and designs for these tunnels are shown on [Plate XXXII]. In this short length of about 977 ft. there are no less than nine different kinds of cross-section. The reason for these changes is the fact that the two lines of track are here not straight and parallel to the center line between the tunnels, but are curved, although symmetrical about this center line. The various changes of section are to enable the tunnels to be built in straight lengths, thus avoiding the disadvantages attending the use of curved forms, and at the same time minimizing the quantity of excavation, an item which accounts for from 60 to 70% of the total cost of tunnels of this type. Of course, there are corresponding and obvious disadvantages in the adoption of many short lengths of different cross-sections, and these disadvantages were well brought out in the course of the work; on the whole, however, they may be said to have justified their adoption. These New York Land Tunnels were divided into three contracts, viz.: From Station 190 + 15 (the Portal to the open work of the Terminal Station at the east side of Tenth Avenue, New York City) to Station 197 + 60, called "Section Gy-East." The next contract, called "Section Gy-West Supplementary," extended from Station 197 + 60 to Station 199 + 20, which is the east side of Eleventh Avenue. The third contract was called "Section Gy-West," and extended from Station 199 + 20 to Station 231 + 78 (the dividing line between the States of New York and New Jersey). Thus, for nearly all its length, this contract consists of shield-driven tunnel. The portion between Stations 199 + 20 and 199 + 91.5, however, was of the Land Tunnel type, and therefore will be included here. A fourth contract extended from Station 231 + 78 to the Weehawken Shaft at Station 263 + 50, and of this all but 230 ft. was of the shield-driven type, only the portion next to the Weehawken Shaft being of the Land Tunnel type.

The four contracts were let to one contractor (The O'Rourke Engineering Construction Company), and the work was carried on simultaneously in all four, so that the division into contracts had no bearing on the methods of work adopted, and these will now be described as a whole and with no further reference to the different sections.

Excavation.

Work was started on the New York side on April 18th, 1904, the Weehawken shaft being at that date still under construction. As will have been noted in the description of the shafts, the contractor found a shaft already prepared for his use, and cross-drifts at grade and at right angles to the future tunnels, and extending across their entire width. The first essential was to get access to the shield chambers, which were to lie about 330 ft. to the west of the shaft, so that the construction of these enlargements in which the shields for the subaqueous tunnels were to be built might be finished as soon as possible and thus allow the earliest possible start to be made with the shield-driven tunnels.

PLATE XXXII.
TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1155.
HEWETT AND BROWN ON
PENNSYLVANIA R. R. TUNNELS: NORTH RIVER TUNNELS.

With this in view, two bottom headings, on the center line of each of the two tracks, were driven westward from the western cross-heading at the foot of the shaft. When about 138 ft. had been made in this way, the two headings were brought together and a break-up was made to the crown level of the tunnel, as the depth of rock cover was doubtful. From this break-up a top heading was driven westward to Station 200 + 30. While widening the heading out at Station 200 + 20 the rock was penetrated on the south side. The exposed wet sand and gravel started to run, and, as a consequence, a change in design was made, the shield chambers (and consequently the start of the shield-driven tunnels) being moved eastward from their original location 133 ft. to their present location. A certain amount of time was necessarily spent in making these changes of design, which involved a rearrangement of the whole layout from the Terminal Station to the start of the River Tunnels. On July 5th, 1904, however, the new design was formally approved. No sooner had this been decided than a strike arose on the work, and this was not settled until August 1st, 1904, but from that time the work progressed without delay. No further reference will be made to the work in the shield chambers, as that will come under the heading of "River Tunnels," being of the segmental, cast-iron lined type.

A top heading was now driven over the original bottom heading west of the shaft, and at the same time the original cross-drifts from the shaft were amalgamated with and broken down by a heading driven at the crown level of the "Intercepting Arch" which here cuts across the ordinary run of tunnel at right angles and affords access to the tunnels from the shafts.

The excavation of the upper portion of the intercepting arch at its southern end gave some trouble, and caused some anxiety, as the rock cover was penetrated and the wet sand and gravel were exposed. This made it necessary to timber all this section heavily, and the tracks of the New York Central Railroad directly above were successfully supported. The general way in which this timbering was carried out will be described under the head of "Timbering."

Meanwhile, the excavation of the tunnels west of the intercepting arch was continued until the North and South Tunnels were taken out to their full outlines, leaving a core of rock between them. This core was gradually removed, and timbering supporting the rock above the middle wall was put in as excavation went on. The ground, which was entirely of micaceous schist, typical of this part of Manhattan, seamed with veins of granite, was rather heavy at the west end, or adjacent to the shield chambers, and required complete segmental timbering across the whole span. One heavy fall of rock in the corewall between the North and South Tunnels took place on November 2d, but fortunately did not extend beyond the limits of the permanent work. On November 7th, 1904, the excavation east of the intercepting arch was begun by driving a bottom heading in the South Tunnel. This was continued to Station 197 + 14 and then was taken up to the crown level and worked as a top heading with the view of keeping track, by making exploratory borings upward from the roof at frequent intervals, of the rock surface, which was here irregular and not known with any degree of certainty. The work was not pressed with any vigor, because all efforts were then being bent toward excavating from the River Tunnels as much rock as possible. In Section Gy-East the conditions were exceptionally variable, as the rock was subject to sudden changes from a soft crumbling mica schist to broad bands of hard granite, and, in addition, the rock surface was very irregular, and, for a good length of this section, was below the crown of the tunnel, a condition which led to the adoption of the cut-and-cover method for part of the work.

The irregularity in conditions called for varying methods of procedure, but in general the methods were as shown on [Plate XXXIII], and described as follows:

In Solid Rock.—Where there was plenty of good rock cover, a top middle heading was driven, which was afterward widened out to the full cross-section of the twin tunnel arches. If necessary, a few lengths of segmental timbering were put in before taking down the bench, which was generally kept some 40 or 50 ft. behind the breast of the heading. After the bench was down, the middle conduit trench was excavated and the trimming done.

In Soft Rock.—Where there was not enough rock cover, or where there was actual soft ground in the roof, wall-plate headings at the springing line level were driven ahead of the remainder of the work. The wall-plates were laid in these, the roof was taken out in short lengths, and segmental timbering spanning from wall-plate to wall-plate was put in. The roof being thus held, the bench excavation proceeded without trouble. Where the rock was penetrated and soft ground showed in the roof, poling boards were driven ahead over the crown-bars, as shown in [Fig. 4].

PLATE XXXIII.
TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1155.
HEWETT AND BROWN ON
PENNSYLVANIA R. R. TUNNELS: NORTH RIVER TUNNELS.

Cut-and-Cover Work.—After some 225 ft. had been driven from the intercepting arch, it was found that the crown of the tunnel was continually in soft ground. To ascertain the extent of this condition the contractor decided to make soundings as far as Tenth Avenue, which was done by sinking trial pits and making wash-borings in the street. These soundings showed that there would be soft ground in the crown from Station 194 + 75 to Station 194 + 25 (at one point to a depth of 12 ft. below the crown), and on each side of this section the cover was insufficient from Station 193 + 58 to Station 195 + 30. This condition being known, it was decided to adopt cut-and-cover work for this length, the principal reasons being that repairs to sewers, streets, and drains would be no more, and probably less, expensive than with the tunnel method; the underpinning of a heavy brick brewery building adjoining the works on the north side would be facilitated, and the opening in the street, through which muck and materials could be handled, would relieve the congested shaft, through which the large volume of muck from the River Tunnels was then being conveyed. On the other hand, the cut-and-cover method was adversely affected by the presence of a heavy timber trestle built down the south side of the street and over which passed all the excavation from the Terminal Station, amounting to a very heavy traffic. As this trestle had to be supported, it complicated the situation considerably. Very little active progress was made between June, 1905, and April, 1906, as the contractor's energies during that time were much taken up with the progress of the shield-driven tunnels. In April, 1906, preparations were made to start a 50-ft. length of open cut, rangers being fixed and sheathing driven; and the sewer which ran down the middle of this street was diverted to the outside of the open-cut length.

April and May were occupied in driving the sheathing down to rock, supporting the trestle, underpinning the adjoining brewery, and excavating the soft material above the rock. On June 2d, 1906, rock was reached, and, by July 31st, the excavation was down to subgrade over nearly the whole 50 ft. in the first length. In the meantime another length was opened up, and eventually a third.

The surface of the rock now seemed to be rising, and the heavy buildings had been passed, so that tunneling was reverted to for the rest of the work, though many difficulties were caused by soft rock in the roof from time to time.

When the excavation for the open-cut work of the Terminal Station had advanced to the line of Tenth Avenue, the contractor started a heading from this point and drove westward under Tenth Avenue until the headings driven eastward from the cut-and-cover portion, were met.

This was done to expedite the work under Tenth Avenue, where the ground was not very good, where there were several important gas and water mains in the street, and where, moreover, the tunnels were of exceptionally large span (24 ft. 6 in.), making a total width of some 60 ft. for the excavation. The excavation for the New York Tunnels was practically finished in January, 1908.

Drilling and Blasting.—The foregoing short description will serve to show in a general way the scheme adopted in making the excavation. A few details on drilling and blasting methods may not be out of place.

Percussive drills run by air pressure were used. They were Ingersoll-Sergeant, Nos. 3½, A-86, C-24, and F-24. The air came from the high-pressure compressor previously described. This compressor, without assistance, could supply air for nine drills, but, when fed by compressed air from the lower pressure, its capacity was increased three or four times.

The air was compressed to 100 lb. per sq. in. in the power-house, and was delivered at about 80 lb. per sq. in. at the drills. A 3-in. air line was used. The drill steel was 1⅛-to 1⅜-in. octagonal. The holes were about 3¼ in. in diameter at starting and 2⅝ in. at the full depth of 10 ft. The powder used on the New York side was 40% Forcite, the near presence of heavy buildings and lack of much rock cover necessitating light charges and many holes spaced close together.

To compensate the contractor for the inevitable excavation done outside the neat lines of the masonry lining, the excavation was paid for to the "Standard Section Line" which was 12 in. outside the neat lines on top and sides and 6 in. outside at the bottom of the cross-section. The actual amount of excavation done was about 11% greater than that paid for. The distance excavated beyond the neat line, because of the very heavy timbering necessary, was about 2.1 ft. instead of the 1 ft. allowed, and at the bottom about 0.85 ft. instead of the 0.50 ft. paid for.

For a period of 5 months detailed records were kept of the drilling and blasting. About 12,900 cu. yd. of excavation are included. A sketch and table showing the method of driving the heading, the number and location of the holes drilled, and the amount of powder used, is given in [Fig. 5]. From this and similar figures the information in [Table 5] is derived.

TABLE 5.

Portion of excavation.Feet of Hole drilled per cubic Yard of ExecavationPounds of Power Used per Cubic Yard of Excavation
15-ft. 4-in. span-- twin tunnel19-ft. 6-in. span-- twin tunnel24-ft. 6-in. span-- twin tunnel15-ft. 4-in.19-ft. 6-in.24-ft. 6-in.
Wall-plate heading[C]13.0010.9710.973.772.852.85
Total heading[C]7.878.177.812.312.021.78
Bench and raker bench[C]5.976.157.560.940.931.13
Trench[C]9.8215.9618.101.842.492.73
Average for section[C]6.697.438.951.281.301.45
Actual amount[D]6.827.278.951.221.241.27

[C] ]Figures taken from typical cross-sections.

[D] This gives the actual amount of drilling done and powder used per cubic yard for the whole period of 5 months of observation, but as this length included 280 ft. of heading and only 220 ft. of bench, the average figures (for powder especially) are too low.

[Table 6] gives the rate and cost of drilling, and the cost of powder. It will be seen that the average rate of drilling was 2.71 ft. per hour per drill or 27.1 ft. per drill per shift.

[Table 7] shows the result of observation as to the time taken in various subdivisions of the drilling operations. These observations were not carried on for a long enough period to give correct results, but the percentages of time spent on each division of the operation are believed to be about right. The headings of this table are self-explanatory. The necessary delays include all time spent in changing bits, making air-line connections, etc. The unnecessary delays are stoppages caused by lack of supplies or insufficient air pressure.

By [Table 6] it will be noticed that the cost of labor for drilling and sharpening steels was about $0.29 per lin. ft. of hole drilled. The total cost, including repairs, supply of air, etc., came to about $0.38, as will be seen from [Table 8].

Timbering.—On the New York side nearly the whole length of the excavation needed timbering, to a greater or less extent, and for the most part required timbering of quite a heavy type.

TABLE 6.—Rock Tunnel Excavation under 32d Street, East of Cut-and-Cover Section. Drilling and Blasting.—Detailed Cost of Labor in Drilling, also Quantity and Cost of Powder Used.

Drilling and Blasting.Powder Used.
Type.Date.Total feet drilled.No. of drill shifts (10-hour.)Feet drilled per man per hour.Quantity of excavation, in cubic yards.Cost of labor only. Drilling and sharpening.Total Quantity.Cost per cubic Yard at 11 cents per pound.
Total.Per linear feet.Per cubic yard
Actual.Paid for.Actual.Paid for
1907HeadingBenchTotalHeadingBenchTotalHeadingBenchTotalActual.[E]Paid for[F]Pounds.
$$$$$$
Ke.May2,9715,5788,549982043023.0312.7342.8311,7361,6642,3310.271.341.401,5950.100.10
June2,0936,1948,287852233082.4622.7772.6918096982,4400.293.013.491,9600.270.31
July7,6277,6272682682.8452.8451,0229602,0310.261.982.119660.100.11
Aug.2,5522,55295952.6882.6887437166400.250.860.894300.060.07
Sept.2,1332,13379792.7002.7002382385330.252.242.242800.130.13
Total5,06424,08429,1481838691,0522.7672.7702.7704,5484,2767,9750.271.751.875,2310.130.13
Ki.May6,9766,9762162163.2293.2296145271,6040.232.613.041,2300.220.26
June4,0894,0891351353.0293.0293572591,2340.303.454.761,0360.320.44
July3,7333,7331401402.6662.6665304041,0840.292.042.685500.110.15
Aug.6,7156,7152492492.7692.7699258901,9010.282.052.139050.100.11
Estim14,74214,742465462.7002.7003,2542,9084,5700.311.401.572,4700.080.09
Total11,06525,19036,2553519351,2863.1522.6942.8195,6804,98810,3930.291.832.086,1910.120.14
Ko.May1,6171,61755552.9212.9212501884710.291.882.503760.170.22
June2,9482,9481071072.7552.7554963478830.291.782.543570.080.11
July3,7343,7341311312.8502.8506266061,0030.271.601.656090.110.11
Aug.8,2608,2602902902.8482.8487092,1610.263.003.049180.140.14
Estim4,7874,7872852851.1801.6806055352,3970.503.964.487620.140.16
Total21,34621,3468688682.4602.4602,6952,3856,9150.322.572.903,0220.120.14
Grand Total16,12970,62086,7495342,6723,2063.0202.7102.71012,92311,64925,2830.291.962.1714,4440.120.14

The work done during the 5 months when these analyzed cost figures were kept includes 280 ft. of bench and 220 ft. of heading. This excess of bench over heading causes the general average amounts per cubic yard to be too low.

[E]Actual amount of excavation.

[F] ]Amount of excavation paid for.

Drilling and Firing Data for Each Sub-division of SectionDrilling and Firing Data for Total Sections
Sub- divisionsVolume of each sub- division paid forNo. of setsNo. of holes in setNo. times firedTotal lbs. of power per hole firedLinear feet of tunnel brokenTotal length drilledTotal length of similar headingsLength drilled per linear foot of tunnelCu yds per linear foot of tunnelTotal feet drilled per cubic yardTotal lbs. of power per linear foot of tunnelTotal lbs. of power per foot drilledTotal lbs. of power per cubic yard
abcdefghijklmno
A17.775[G]1634.50Σ(c + d) ÷ g(b + i) ÷ gj ÷ k(c + d + f) ÷ gm ÷ jm ÷ k
[H]1911.50
[I]1611.00
[J]1610.756.0195265.005.92510.9717.000.2612.848
A'1.0023-410.255.02128.400.40021.000.700.1661.750
B5.925[G]23-411.004.035217.502.9625.903.500.2001.181
C[K]1321.125
33.334711.1255.0186137.206.6665.586.9750.1871.046
D6.66525-610.753.033222.004.4444.955.5000.2501.237
Total for Heading150.1020.3977.8133.6750.2271.778
E50.009511.505.0405181.0010.0008.1013.5000.1671.350
F88.8810.5421.50
[L]5.0411.504.06821170.5022.2227.6723.2300.1361.046
G22.225.5421.005.0132126.404.4445.944.4000.1660.990
Total for Bench277.9036.6667.5641.1500.1501.133
H9.775310.50
4610.506.0156126.001.62815.963.2500.1251.995
I26.668511.006.0252284.004.44418.9013.3330.1583.000
Total of Trench110.006.07218.1016.5830.1512.731
Total for Whole Section548.0063.1358.9591.4080.1721.446
Powder taken at 0.5 lb. per stick

[G] ]6 Cut Holes-8 feet (Black circle)

[H] ]9 First Side Rd. and Bottom-7 feet (Circle with dot in it)

[I] ]6 Back Round-7 feet (Circle with line in it)

[J] ]6 Top Back Round-7 feet (Circle with x in it)

[K] ]A' 7 Holes-3 feet (Open circle)

[L] ]line holes (Plus sign)

TABLE 7.—Analysis of Drilling Time on Section Gy-East.

Position in Section.Nature of Rock.No. of Drill Shifts observed for average.Average Time Taken:Feet Drilled.
Setting up.Drilling.Necessary delays.Unnecessary delays.Taking down machine.Loading and firing.Total drilling.Mucking.Total.Per shift.Per working hour.
h. m.h. m.h. m.h. m.h. m.h. m.h. m.h. m.h. m.
HeadingQuartz80:384:521:400:050:047:192:4110:0022:002.86
HeadingHard mica schist10:158:001:4510:0010:0042.04.20
BenchQuartz231:235:572:230:050:050:0710:0010:0025.92.59
BenchMedium mica schist161:106:081:500:120:070:079:340:2610:0022.222.32
Center trenchMedium mica schist100:585:531:330:060:120:309:120:4810:0022.02.39
Center trenchSoft mica schist91:106:401:170:100:200:2310:0010:0026.442.64
General average671:085:581:530:070:090:129:270:3310:0024.12.54
Percentage11.3%59.7%18.9%1.1%1.5%2%94.5%5.5%100%

TABLE 8.--Analyzed Cost of Drilling.

Item of Cost.Cost per Foot of Hole DrilledCost per drill shift
15 ft. 4 in.19 ft. 6 in.24 ft. 6 in.Average.15 ft. 4 in.19 ft. 6 in.24 ft. 6 in.Average.
Drilling labor$0.25$0.28$0.31$0.28$6.95$7.75$7.60$7.45
Sharpening0.020.020.010.0160.580.420.340.43
Drill steel (5 in. per drill shift)0.0070.0070.0060.0070.190.200.150.19
Drill repairs0.020.020.020.020.610.590.420.54
High-pressure air[M]0.050.040.070.071.391.861.671.82
Totals$0.35$0.38$0.41$0.385$9.67$10.82$10.18$10.43

[M] This is an estimated figure, ascertained by taking a proportion of the whole charge for plant running.

General Methods.—Whenever any considerable support was needed for the ground, segmental timbering was used. In most cases, this was supported by wall-plates at the springing line, and was set with an allowance for settlement, so that it would be clear of the work when the masonry lining was put in. As the twin-tunnel section involved the excavation of the North and South Tunnels at the same time, the cross-section of the upper part of the excavation consisted of two quadrants rising from the springing line and connected at the top by a horizontal piece from 19 to 28 ft. in length. This made a rather flat arch to support by timbering.

The timber for the segmental work was 12 by 12-in. yellow pine. In light ground the bents were spaced at 5-ft. centers, in heavy ground 2-ft. 6-in. centers.

When the soft ground in the roof was struck, posts had to be used in the heading to support the caps. When the bench was removed, the posts were replaced by others down to the bottom of the excavation. These long posts were a great hindrance to all the work, and each replacement of short posts by long ones meant a settlement of the caps; consequently, it was decided to use in the section east of the cut-and-cover, where all the ground was heavy, a temporary inner bent of segmental timber, within and reinforcing the permanent bent, and resting on separate wall-plates. This is shown by [Fig. 6]. These temporary bents were inside the work, and were removed as the arch was built. However, the caps settled considerably in some cases, so that it was not possible to do away with posting entirely.

In heavy ground the caps were set about 1 ft. above the neat line of the crown of the brick arch, in some cases they were set only 6 in. above, but the settlement was often more than this, causing great trouble in cutting out the encroaching timber when the arch had to be built.

In the tunnels east of the cut-and-cover portion, wall-plate headings were driven (shown by areas marked Aon [Fig. 5]), and, when a length of wall-plate had been set, the full-width heading was advanced a foot or two at a time, the timber segmental bents being set up as soon as possible; lagging was then driven over the cap into the soft ground. [Fig. 6] shows the double set of segmental bents adopted in the 15-ft. 4-in. twin tunnels east of the cut-and-cover section.

When the soft ground came down so low as to interfere with the excavation of the wall-plate headings, a small heading was driven into the soft ground on the line of the ends of the caps, and lagging was driven down from this to the wall-plate heading, as illustrated in [Fig. 4].

In the 19-ft. 6-in. tunnels the wall-plate for the inner bent was supported by a side-bench, termed the "Raker" bench. This was left in position until the rest of the bench and the middle subgrade conduit trench had been excavated; it was then possible to support the caps by two rows of posts from subgrade level, take out the inner bents, and excavate the raker bench.

The 24-ft. 6-in. twin tunnels, which are at the extreme eastern end of this section, adjoining the open-cut work of the Terminal Station, and under Tenth Avenue, were driven from the Terminal Station-West, and the timbering had to be made very secure on account of the pipes and sewers in the street above. Detailed records were kept of the amount of timber used and the cost of labor and material expended in timbering. These records cover the same portion of tunnel as that for which the detailed records of drilling costs, previously referred to, were kept. These records are shown in [Tables 9] and [10]. It will be noted that the timber used in blocking, that is, filling up voids outside the main timbering, amounted to more than two-thirds of the total timber, and that the cost of labor in erecting the timbering exceeds the prime cost of the timber by about one-third. The following distinction is made between permanent and temporary timbering: The permanent timbering is that which is concreted in when the masonry is built; the temporary consists of the lower bents and posts, which have to be removed when the masonry is built.

Force Employed in Excavation.—A typical day's working force for drilling, blasting, mucking, and timbering is shown in [Table 11].

Where there was any large quantity of soft ground in the roof, the timber gang was much larger than shown in [Table 11], and was helped by the mucking gang. The drillers did most of the mucking out of the heading before setting up the drills.

Excavation of Weehawken Rock Tunnels.—This subject may be dismissed in a few words, as very few features of interest were called into play. The rock was of good quality, being the sandstone typical of this part of the country. Little or no timbering was needed, there were no buildings above the tunnel to be taken care of, and large charges of powder could be used.

TABLE 9.— Supplementary Analysis of Timbering, Rock Tunnel Excavation Under 32d Street, East of Cut-and-Cover Section. Analyzed Cost of Timbering, per Foot Run and per Bent.

Ke
Per foot run of tunnelPer bent, 3 ft, 6 in., center to centerPer cubic yard excavation
PERMANENT TIMBERING.
Lumber in feet, B. M.
Upper Bent.2746857.8
Blocking.2947358.3
Total.5681,42016.1
Cost, in dollars.
Lumber.23.7559.380.67
Labor.37.5093.751.06
Total.61.25153.131.73
TEMPORARY TIMBERING.
Lumber in feet, B. M.
Lower Bent.47911.9713.6
Blocking.1934835.5
Total.67216.8019.1
Cost, in dollars.
Lumber.29.1372.810.82
Erection labor.28.8572.130.82
Removal labor.8.2920.730.23
Total labor.37.1492.861.05
Total.66.27165.671.87
GRAND TOTAL.
Lumber in feet, B. M.1,2403,10035.2
Cost, in dollars.
Lumber.52.88132.191.49
Labor.74.64186.613.60
Total.127.52318.80
Ki
Per foot run of tunnelPer bent, 3 ft, 6 in., center to centerPer cubic yard excavation
PERMANENT TIMBERING.
Lumber in feet, B. M.
Upper Bent.2278305.3
Blocking.1646013.8
Total.3911,4319.1
Cost, in dollars.
Lumber.16.8461.560.39
Labor.12.8246.880.30
Total.29.66108.440.69
TEMPORARY TIMBERING.
Lumber in feet, B. M.
Lower Bent.186.33681.254.33
Blocking.42.80156.500.99
Total.229.13837.755.32
Cost, in dollars.
Lumber.9.6535.310.22
Erection labor.10.3837.970.24
Removal labor.9.7434.090.23
Total labor.20.1272.060.47
Total.29.77107.370.69
GRAND TOTAL.
Lumber in feet, B. M.6.2022.6914.4
Cost, in dollars.
Lumber.26.4996.870.61
Labor.32.94118.940.77
Total.59.43215.811.38
Ko
Per foot run of tunnelPer bent, 3 ft, 6 in., center to centerPer cubic yard excavation
PERMANENT TIMBERING.
Lumber in feet, B. M.
Upper Bent.2619624.1
Blocking.4081,5086.5
Total.66924.7010.5
Cost, in dollars.
Lumber.28.00103.380.44
Labor.29.79110.000.47
Total.57.79213.380.91
TEMPORARY TIMBERING.
Lumber in feet, B. M.
Lower Bent.3501,2915.5
Blocking.612271.0
Total.4111,5186.5
Cost, in dollars.
Lumber.18.4568.160.29
Erection labor.20.8376.920.33
Removal labor.12.1644.590.19
Total labor.32.99121.510.52
Total.51.44189.670.81
GRAND TOTAL.
Lumber in feet, B. M.1,0803,98817.1
Cost, in dollars.
Lumber.46.45171.540.73
Labor.62.78231.500.99
Total.109.23403.041.72

TABLE 10.—Timbering:—Detailed Cost of Timber, Labor, and Superintendence. Rock Tunnel Excavation under 32d Street, East of Cut-and-Cover Section.

Date.Timber Used, in Feet, B. M.Excavation in Cubic Yards.Cost of Timber.Cost of Labor.Total Cost.Cost per Cubic Yard (Actual).Cost per Cubic Yard (Paid for).Cost, per 1,000 Ft., B. M., of Total Timber.
Main timber.Blocking timber.Total timber.Actual.Paid for.Main.Block.Total.Timber.Labor.Total.Timber.Labor.Total.Total timber.Labor.Total.
1907abcdefghijh / di / dj / dh / ei / ej / eh / ci / cj / c
KeMay18,01615,23433,2501,7361,664$810$565$1,375$1,792$3,167$0.79$1.03$1.82$0.82$1.07$1.90$41.35$53.89$95.24
June14,04811,52825,5768096986804571,0871,5762,6631.341.953.291.552.253.8142.5061.62104.12
July20,0927,33927,4311,0229609003001,2001,5802,7801.161.552.721.251.642.8943.7457.60101.34
August6,4852,6329,1177437162901104003007000.530.400.940.570.410.9843.8732.9076.77
Sept.1,6322,2243,8562382387394167602270.700.250.950.700.250.9543.3115.5658.87
Removal663663
Total60,27338,95799,2304,5484,276$2,703$1,526$4,229$5,971$10,200$0.91$1.51$2.22$1.00$1.40$2.40$42.62$60.19$102.81
KiMay3,5373,537614527$150$150$100$250$0.24$0.16$0.40$0.28$0.19$0.47$42.41$28.27$70.68
June300300357259$141444580.040.120.160.050.170.2246.66146.33193.33
July7,7765,81113,5875304043502335835257,1081.100.992.091.441.302.7442.9138.6481.54
August19,7125,70225,4149258908872201,1071,0182,1251.201.102.301.241.142.3843.5640.0683.61
Sept.20,5569,21829,7741,5851,5019253251,2501,0282,2780.790.651.440.830.681.5141.9834.5376.51
Removal1,6691,4071,1391,1390.680.680.810.81
Total48,34424,26872,6125,6804,988$2,176$928$3,104$3,854$6,958$0.55$0.68$1.23$0.63$0.77$1.40$42.75$53.09$95.84
KoMay4,3328,78813,120250188$175$366$561$303$864$2.24$1.21$3.45$3.00$1.61$4.61$42.76$23.10$65.86
June7,13210,01717,1494963473243967205621,2821.451.182.582.071.613.6841.9832.7774.75
July3,0702003,270626606134101441563000.230.250.480.230.260.4944.0447.7091.74
August10,7042,10212,806718709481805617271,2880.781.011.790.801.021.8243.8056.77100.57
Sept.2,4002452,64539632410881164005160.291.011.300.361.231.5943.85151.23195.08
Removal2092115355352.562.562.542.54
Total27,63821,35248,9902,6952,385$1,242$860$2,102$2,683$4,785$0.78$1.00$1.78$0.88$1.12$2.00$42.91$54.75$97.65
Grand total136,25584,577220,83212,92311,649$6,121$3,314$9,435$12,508$21,943$0.73$0.97$1.70$0.81$1.07$1.88$42.73$56.65$99.38

Work was begun on September 1st, 1904, immediately on the completion of the work on the shaft. The North and South Tunnels in this case are completely independent, as will be seen from [Plate XXXIV]. The procedure adopted was to drive a top heading on the center line of each tunnel and to break down the bench from this. The drilling was at first supplied with steam power from a temporary plant, as the contractor was at that time installing his permanent plant, which was finished at the end of November, 1904. At this time the rate of advance averaged 3½ lin. ft. of full section per day of 24 hours. By the end of January the Weehawken rock tunnels were completely excavated, and by the middle of April, 1905, the excavation for the shield chambers was finished; the erection of the shields was started at the end of that month.

TABLE 11.

Grade. Total No. Rate per day. Drilling and blasting: No. Mucking: No. Timbering: No.
Superintendent 1 $7.70 ½
Assistant engineer 1 5.80 ½
Electrician 1 3.50 ½
Engineer 1 3.50 1
Signalman 1 2.00 1
Foreman 3 4.00 1 1 1
Driller 5 3.00 5
Driller's helper 5 2.00 5
Laborers 14 2.00 14
Timbermen 3 3.00 3
Timbermen's helpers 4 2.00 4
Machinist 1 4.00 1
Blacksmith 2 3.50 2
Blacksmith's helper 2 2.00 2
Nipper 2 2.00 2
Waterboy 1 2.00 1
Total 47 20½ 17⅜ 9⅛

The general scheme of excavation is shown by Plate [XXXIII]. The bench was kept 50 or 60 ft. behind the face of the heading. The powder used was 60% Forcite. The general system of drilling was as shown in [Fig. 7]. The average length of hole drilled per cubic yard of excavation was 2.9 ft., as against 7.70 ft. at Manhattan; and the amount of powder used was 1.96 lb. per cu. yd., as against 1.24 lb. at Manhattan. There was little timbering. A length of about 30 or 40 ft. adjoining the Weehawken shaft was timbered, and also a shattered seam of about 17 ft. in width between Stations 262 + 10 and 262 + 27.

The two entirely separate tunnels gave a cross-section which was much more easily timbered than the wide flat span at Manhattan, and the segmental timbering was amply strong without posts or other reinforcement.

[Table 12] is a summary of the cost of excavating the Land Tunnels, based on actual records carefully kept throughout the work.

TABLE 12.—Cost of Excavation of Land Tunnels, in Dollars per Cubic Yard.

Manhattan.Weehawken.Total yardage and average cost.
Cubic yards excavated43,2898,31151,600
Labor.
Surface transport$0.49$0.87$0.55
Drilling and blasting2.371.552.24
Mucking2.492.082.42
Timbering0.870.180.76
Total labor$6.22$4.68$5.97
Material.
Drilling$0.15$0.15$0.15
Blasting0.210.210.21
Timber0.390.200.36
Total material$0.75$0.56$0.72
Plant running$0.76$0.65$0.74
Surface labor, repairs and maintenance0.150.080.14
Field office administration1.051.181.07
Total field charges$8.96$7.15$8.64
Chief office administration$0.34$0.38$0.34
Plant depreciation0.661.010.72
Street and building repairs0.270.23
Total average cost per cubic yard$10.23$8.54$9.93

Masonry Lining of Land Tunnels.

[Plates XXXII] and [XXXIV] show in detail the tunnels as they were actually built. It will be seen that in all work, except in the Gy-East contract, there was a bench at each side of each tunnel in which the cable conduits were embedded. In Gy-East the bank of ducts which came next to the middle wall was carried below subgrade, and the inner benches were omitted.

The side-walls and subgrade electric conduits were water-proofed with felt and pitch. The water-proofing was placed on the outside of the side-walls (that is, on the neat line), and the space between the rock and the water-proofing was filled with concrete. This concrete was called the "Sand-Wall."

The general sequence of building the masonry lining is shown in [Fig. 8]. The operations were as follows:

1.—Laying concrete for the whole height of the sand-walls, and for the floor and foundations for walls and benches up to the level of the base of the conduits;

2.—Water-proofing the side-walls, and, where there was a middle trench containing subgrade conduits, laying and water-proofing these conduits;

3.—Building concrete wall for conduits to be laid against, and, where there was a middle trench, filling up with concrete between the conduits;

4.—Laying conduits;

5.—Laying concrete for benches and middle-wall;

6.—Building haunches from top of bench to springing of brick arch;

7.—Building brick arch and part of concrete back-filling;

8.—Finishing back-filling.

The whole work will be generally described under the headings of Concrete, Brickwork, Water-proofing, and Electric Conduits.

Concrete.—The number of types and the obstructions caused by the heavy posting of the timbering made it inadvisable to use built-up traveling forms at the Manhattan side, though they were used in the Weehawken Rock Tunnels.

The specifications required a facing mixture of mortar to be deposited against the forms simultaneously with the placing of the concrete. This facing mixture was dry, about 2 in. thick, and was kept separate from the concrete during the placing by a steel diaphragm. The diaphragm was removed when the concrete reached the top of each successive layer, and the facing mixture and concrete were then tamped down together. This method was at first followed and gave good results, which was indeed a foregone conclusion, as the Weehawken shaft had been built in this way. However, it was found that as good results, in the way of smooth finish, were to be obtained without the facing mixture by spading the concrete back from the forms, so that the stone was forced back and the finer portion of the mixture came against the forms; this method was followed for the rest of the work. All corners were rounded off on a 1-in. radius by mouldings tacked to the forms. The side-bench forms were used about four times, and were carefully scraped, planed, filled at open joints, and oiled with soap grease each time they were set up. When too rough for face work they were used for sand-wall and other rough work.

PLATE XXXIV.
TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1155.
HEWETT AND BROWN ON
PENNSYLVANIA R. R. TUNNELS: NORTH RIVER TUNNELS.

The mixing was done by a No. 4 Ransome mixer, driven by 30-h.p. electric motors. The mixer at Manhattan was set on an elevated platform at the north end of the intercepting arch; that at Weehawken was placed at the entrance to the tunnels. The sand and stone were stored in bins above the mixers, and were led to the hoppers of the mixers through chutes. The hoppers were divided into two sections, which gave the correct quantities of sand and stone, respectively, for one batch. The water was measured in a small tank alongside. A "four-bag" batch was the amount mixed at one time, that is, it consisted of 4 bags of cement, 8¾ cu. ft. of sand, and 17½ cu. ft. of broken stone, and was called a 1 : 2½ : 5 mixture. It measured when mixed about ¾ cu. yd.

The cement was furnished to the contractor by the Railroad Company, which undertook all the purchasing from the manufacturer, as well as the sampling, testing, and storing until the contractor needed it. The Railroad Company charged the contractor $2 a barrel for this material.

The sand was required by the specifications to be coarse, sharp, and silicious, and to contain not more than 0.5% of mica, loam, dirt, or clay. All sand was carefully tested before being used. The stone was to be a sound trap or limestone, passing a 1½-in. mesh and being retained on ⅜-in. mesh. The contractor was allowed to use a coarser stone than this, namely, one that had passed a 2-in. and was retained on a 1½-in. mesh.

The concrete was to be machine-mixed, except in cases of local necessity. The quantity of water used in the mixture was to be such that the concrete would quake on being deposited, but the engineer was to use his discretion on this point. Concrete was to be deposited in such a manner that the aggregates would not separate. It was to be laid in layers, not exceeding 9 in. in thickness, and thoroughly rammed. When placing was suspended, a joint was to be formed in a manner satisfactory to the engineer. Before depositing fresh concrete, the entire surface on which it was to be laid was to be cleaned, washed and brushed, and slushed over with neat cement grout. Concrete which had begun to set was not to be used, and retempering was not to be allowed.

The forms were to be substantial and hold their shape until the concrete had set. The face forms were to be of matched and dressed planking, finished to true lines and surfaces; adequate measures were to be taken to prevent concrete from adhering to the forms. Warped or distorted forms were to be replaced. Plastering the face was not allowed. Rock surfaces were to be thoroughly washed and cleaned before the concrete was deposited.

These specifications were followed quite closely.

A typical working gang, as divided among the various operations, is shown below:

Superintendence.
½Superintendent@$250permonth
½Assistant engineer"150""
1Assistant superintendent"150""
Surface Transport.
1Foreman@$2.50perday
1Engineer"3.00""
1Signalman"2.00""
16Laborers"1.75""
3Teams"7.50""
Laying.
1Foreman@$4.00perday
8Laborers"2.00""
Forms.
1Foreman@$4.50perday
4Carpenters"3.25""
5Helpers"2.25""
Tunnel Transport.
¼Foreman@$3.25perday
¼Engineer"3.00""
¼Signalman"2.00""
4Laborers"1.75""
Mixers.
¼Foreman@$3.25perday
2Laborers"1.75""

The superintendent and assistant engineer looked after the brickwork and other work as well as the concrete. The surface transport gang handled all the materials on the surface, including the fetching of the cement from the cement warehouses.

The tunnel transport gang handled all materials in the tunnel, but, when the haul became too long, the gang was reinforced with laborers from the laying gang. Of the laying gang, two generally did the spading, two the spreading and tamping, and the remaining force dumped the concrete. The general cost of this part of the work is shown in [Table 13].

The figures in [Table 13] include the various items built into the concrete and some that are certificate extras in connection with the concrete, such as drains, ironwork and iron materials, rods and bars, expanded metal, doors, frames and fittings, etc.

Water-proofing.—According to the specifications, the water-proofing was to consist of seven layers of pitch and six layers of felt on the side-walls and a ½-in. layer of mastic, composed of coal-tar and Portland cement, to be plastered over the outside of the arches.

By the time the work was in hand, some distrust had arisen as to the efficiency of this mastic coating, and a great deal of study was devoted to the problem of how to apply a felt and pitch water-proofing to the arches. The difficulty was that there was no room between the rock and the arch or between the timber and the arch (as the case might be) in which to work. Several ingenious schemes of putting the felt on in layers, or in small pieces like shingles, were proposed and discussed, and a full-sized model of the tunnel arch was even built on which to try experiments, but it was finally decided to overcome the difficulty by leaving out the arch water-proofing altogether, and simply building in pipes for grouting through under pressure, in case it was found that the arch was wet.

As to the arch built through the length excavated by cut-and-cover on the New York side, it was resolved to water-proof that with felt and pitch exactly as the side-walls were done, the spandrel filling between the arches being raised in a slight ridge along the concrete line between tunnels in order to throw the water over to the sides. The portions of arch not water-proofed were rather wet, and grouting with a 1:1 mixture was done, but only with the effect of stopping large local leaks and distributing a general dampness over the whole surface of the arch.

TABLE 13.—Cost of Concrete in Land Tunnels, in Dollars per Cubic Yard.

Manhattan.Weehawken.Total yardage.
Cubic yards placed14,706½3,72318,429½
Labor.Average Cost per Cubic Yard.
Surface transport$0.31$1.43$0.54
Superintendence and general labor at point of work0.311.310.51
Mixing0.520.560.53
Laying1.381.451.39
Tunnel transport1.301.471.34
Cleaning0.210.17
Forms: erecting and removal1.581.511.56
Total labor$5.61$7.73$6.04
Material.
Cement$2.30$2.22$2.28
Sand0.340.400.36
Stone0.910.610.85
Lumber for forms0.470.450.47
Sundry tunnel supplies0.160.170.16
Total materials$4.18$3.85$4.12
Plant running$0.44$0.44$0.44
Surface labor, repairs and maintenance0.251.240.44
Field office administration0.501.720.75
Total field charges$10.98$14.98$11.79
Plant depreciation$0.62$1.57$0.81
Chief office administration0.240.310.25
Total average cost per cubic yard$11.84$16.86$12.85
Cost of Miscellaneous Items in Concrete.
Manhattan.Weehawken.Average.
Cubic yards14,706½3,72318,429½
Amount, in dollars$6,184.83$1,756.79$7,941.62
Unit cost0.420.470.43

The 24-ft. 6-in. tunnel adjoining the Terminal Station-West was water-proofed by a surface-rendering method which, up to the present time, has been satisfactory. Generally speaking, the arches of the Land Tunnels, though not dripping with water, are the dampest parts of the whole structure from Tenth Avenue to Weehawken, and it would seem as if some form of water-proofing over these arches would have been a distinct advantage.

There was no difficulty in applying the water-proofing on the side-walls, after a little experience had been gained as to the best methods. The specifications required the sand-wall to be covered with alternate layers of coal-tar pitch and felt, seven layers of the former and six layers of the latter, the felt to be of Hydrex brand or other equally satisfactory to the engineer. The pitch was to be straight-run, coal-tar pitch which would soften at 60° Fahr., and melt at 100° Fahr., being a grade in which distillate oils, distilled from it, should have a specified gravity of 1.105. The pitch was to be mopped on the surface to a uniform thickness of 1/16 in., and a covering of felt, previously mopped with pitch, was to be applied immediately. The sheets were to lap not less than 4 in. on cross-joints and 12 in. on longitudinal joints, and had to adhere firmly to the pitch-covered surface. This layer was then to be mopped, and another layer placed, and so on until all the layers were in place. This water-proofing was to extend from the bottom of the cable conduits to the springing of the brick arch. Where sub-track conduits were used, these were to be surrounded with their own water-proofing. The work was carried out as specified; the sand-walls were not rendered, but were built smooth enough to apply the water-proofing directly to them. They were dried with gasoline torches before the application of the pitch, and in very wet sections grooves were cut to lead the water away.

The first attempts were with the felt laid in horizontal strips. This ended very disastrously, as the pitch could not sustain the weight of the felt, and the whole arrangement slipped down the wall. The felt was then laid vertically, being tacked to a piece of horizontal scantling at the top of the sand-wall and also held by a row of planks braced against it at about half its height. A layer of porous brick was laid as a drain along the base of the water-proofing, covered by a single layer of felt to prevent it from becoming choked with concrete.

The water-proofing of the sub-track conduits was troublesome, as the numerous layers and the necessity for preserving the proper laps in both directions between adjacent layers made the whole thing a kind of Chinese puzzle. Various modifications, to suit local conditions, were made from time to time. Conduits outside the general outline of the tunnel are difficult to excavate, to lay, and to water-proof, and should be avoided wherever possible.

The usual force in water-proofing consisted of a foreman, at $3.50 per day, and nine laborers at $1.75 per day. These men not only laid the water-proofing, but transported the materials, heated the pitch, and cut up the rolls of felt. In general, two men transported material, one tended the heater, and the other six worked in pairs, two preparing the surface of the concrete sand-wall, two laying pitch, and two laying felt.

The cost of the water-proofing operation was about as shown in [Table 14].

TABLE 14.— Cost of Water-Proofing, in Dollars per Square Foot.

Manhattan.Weehawken.Total.
Square feet covered47,04213,96460,736
Average cost per square foot.
Labor$0.07$0.07$0.07
Material0.120.090.11
Total field charges$0.19$0.16$0.18
Chief office and plant depreciation0.010.030.02
Total average cost$0.20$0.19$0.20

Brickwork in Arches.—Owing to the heavy timbering, the brickwork at Manhattan was interfered with to a considerable extent, and the gang was always kept at work at two or more places. The work was carried up to a point where it was necessary to back-fill, or prop or cut away encroaching timbers, and then the men were moved to another place while this was being done.

The centers were set up in sets of seven, spaced 4 ft. apart. Two 14-ft. lengths of 3 by 4-in. yellow pine lagging were used with each set of ribs, with 24 by 8-in. block lagging in the crown.

All centers were set ¼ in. high, to allow for settlement, except in the 24-ft. 6-in. span, in which they were set ½ in. high. This proved ample, the average settlement of the ribs being 0.01 ft. and of the masonry, 0.003 ft. In the 24-ft. 6-in. span the ribs were strengthened with 6 by 6-in. blocking and 12 by 12-in. posts to subgrade. Great trouble was here encountered with encroaching timbering, due to the settlement of the wide flat span. Grout pipes were built in, as previously mentioned.

Each mason laid an average of 0.535 cu. yd. of brickwork per hour, or 4.28 cu. yd. per day. The number of bricks laid per mason per hour was 218, or 1,744 per day.

The bricks were of the best quality of vitrified paving brick, and were obtained from the Jamestown Brick Company, of Jamestown, N. Y. The average size was 8¾ by 3-15/16 by 2-7/16 in.; the average number per cubic yard of masonry was 408, the arches being from 19 ft. to 24 ft. 6 in. in span and from 22 to 27 in. thick. The joints were 3/16 in. at the face and averaged 9/16 in. through the arch.

The proportions for mortar were 1 of cement and 2½ of sand. One cubic yard of masonry was composed of 73.5% brick and 26.5% mortar. The volume of the ingredients in a four-bag batch was 12.12 cu. ft., and the resulting mixture was 9.54 cu. ft. The number of barrels of cement was 0.915 per cu. yd. of masonry, and about 17.7% of the mortar made was wasted. The average force employed was:

Laying.
1Foreman@$8.00perday
4Layers"6.00""
8Tenders"2.00""
2Mixers"2.00""
Forms.
1Foreman@$4.50perday
4Carpenters"3.50""
5Helpers"2.25""
Transport.
¼Hoist engineer@$3.00perday
¼Signalman"2.00""
4Laborers"2.00""

For materials, the following prices prevailed:
Cement, $2.00 per bbl.,
Sand, $0.90 to $1.00 per cu. yd.,
Brick, $16.00 per thousand, delivered at yard,
Centers, $26.00 each,
Lagging, $45.00 per 1,000 ft. B. M.

The cost of the brickwork is given in Table 15.

TABLE 15.—Cost of Brickwork.

Manhattan.Weehawken.Total.
Cubic yards placed4,1377904,927
Labor.Average Cost per Cubic Yard.
Surface transport$0.35$1.19$0.48
Superintendent and general labor at point of work0.170.040.16
Laying and mixing2.583.202.60
Forms: erection and removal2.620.322.25
Tunnel transport1.191.121.18
Total labor$6.91$5.87$6.75
Material.
Brick$6.56$6.56$6.56
Cement1.761.751.76
Sand0.200.280.22
Forms0.920.980.98
Overhead conductor pockets0.150.090.13
Total material$9.59$9.66$9.60
Plant running$0.55$0.30$0.51
Surface labor, repairs and maintenance0.361.300.51
Field office administration0.550.880.60
Total field charges$17.96$18.01$17.97
Chief office administration$0.60$0.66$0.61
Plant depreciation0.350.640.39
Total average cost per cubic yard$18.91$19.31$18.97

In [Table 16] the cost of grout is expressed in terms of barrels of cement used, because in the schedule of prices attached to the contract, that was the unit of payment for grout.

TABLE 16.—Cost of Grout Over Arches in Land Tunnels.
Cost, in Dollars per Barrel of Cement Used.

Manhattan. (Gy-East only.)Weehawken.Total.
Barrels used3,000½261½3,262
Average Cost per Barrel of Cement Used.
Labor$0.55$0.46$0.53
Material2.302.252.28
Field office administration0.080.060.08
Plant and supplies0.100.070.09
Total field charges$3.03$2.84$2.98
Chief office and plant depreciation0.210.220.28
Total average cost$3.24$3.06$3.20

Vitrified Earthenware Conduits for Electric Cables.—The general drawings will show how the ducts were arranged, and that manholes were provided at intervals. They were water-proofed, in the case of those embedded in the bench, by the general water-proofing of the tunnels, which was carried down to the level of the bottom of the banks of ducts; and in the case of those below subgrade, by a special water-proofing of felt and pitch wrapped around the ducts themselves.

The portion of wall in front of the ducts was bonded to that behind by bonds, mostly of expanded metal, passing between the ducts. Examples of the bonding will be seen in the drawings.

The joints between successive lengths of 4-way and 2-way ducts were wrapped with two thicknesses of cotton duck, 6 in. wide, those of single-way ducts were not wrapped, but plastered with cement mortar. The ducts were laid on beds of mortar, and were made to break joints at top and bottom and side to side with the adjacent ducts. They were laid with a wooden mandrel; a square leather washer at the near end acted as a cleanser when the mandrel was pulled through.

The specifications required the ducts to be laid at the same time as the concrete and be carried up with it, but this was found to be a very awkward operation, as the tamping of the concrete and the walking of men disturbed the ducts, especially as the bonds lay across them. It was resolved, therefore, to build the portion of the wall behind the ducts first, with the bonds embedded in it at the proper heights and projecting from it, then to lay up the banks of ducts against this wall, bending the bonds down as they were reached, and finally, after all the ducts were in, to lay the concrete in front of and over the top of the ducts. Several detailed modifications of this general scheme were followed at one time or another when necessary or advisable.

The laying of ducts below subgrade was not complicated by the presence of bonds, the water-proofing caused the trouble here, as before described.