This e-text includes a few characters that will only display in UTF-8 (Unicode) file encoding:
⅛ ⅜ ⅝ ⅞ †
If any of these characters do not display properly, or if the quotation marks in this paragraph appear as garbage, you may have an incompatible browser or unavailable fonts. First, make sure that the browser’s “character set” or “file encoding” is set to Unicode (UTF-8). You may also need to change your browser’s default font.
Two other papers from ASCE Transactions LXVIII (September 1910) are referenced in this paper:
No. 1150, “The New York Tunnel Extension...” by Charles W. Raymond, available from Project Gutenberg as [e-text 18229].
No. 1151, “The North River Division” by Charles M. Jacobs, [e-text 18548], generally cited as “the paper by Mr. Jacobs”.
The word “Figure” is used in two ways. It refers either to individual numbered Figures (1-21), or to any of the four pictures that make up each Plate, identified in the form “Fig. 2, Plate XXI”. Figures 1-4 are always discussed as a group.
Larger Figures are shown as thumbnails, followed by inline enlargements or links. If your browser supports image mapping, some of the more complicated Figures can be clicked directly.
[ List of Illustrations] (added by transcriber)
AMERICAN SOCIETY OF CIVIL ENGINEERS
INSTITUTED 1852
TRANSACTIONS
Paper No. 1154
THE NEW YORK TUNNEL EXTENSION OF THE PENNSYLVANIA RAILROAD.
THE BERGEN HILL TUNNELS.[1]
By F. Lavis, M. Am. Soc. C. E.
[Location.]—That section of the Pennsylvania Railroad’s New York Tunnels lying west of the Hudson River is designated Section “K,” and the tunnels are generally spoken of as the Bergen Hill Tunnels. Bergen Hill is a trap dike (diabase) forming the lower extension of the Hudson River Palisades.
There are two parallel single-track tunnels, cross-sections of which are shown on Plate VIII of the paper by Charles M. Jacobs, M. Am. Soc. C. E. The center line is a tangent, and nearly on the line of 32d Street, New York City, produced, its course being N. 50° 30' W. The elevation of the top of the rail at the Weehawken Shaft (a view of which is shown by Fig. 2, [Plate XXII]), on the west bank of the Hudson River, is about 64 ft. below mean high water; and at the Western Portal, or Hackensack end, the rail is about 17 ft. above; the grade throughout is 1.3%, ascending from east to west. The length of each tunnel between the portals is 5,920 ft.
A general plan and profile of these tunnels is shown on Plate I of the paper by Charles W. Raymond, M. Am. Soc. C. E. At
Central Avenue a shaft 212 ft. deep was sunk. It is 3,620 ft. from the Weehawken Shaft.
PLATE XXI.
TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1154.
LAVIS ON
PENNSYLVANIA R.R. TUNNELS: BERGEN HILL TUNNELS.
Fig. 1. K 94. P.R.R. Tunnels, N. R. D. Section K. (Bergen Hill Tunnels.) from Hackensack Poral, North Cut and Cover Section, and Portal looking East from Sta. 323. Dec. 8, 05.
Fig. 2. K 71. P.R.R. Tunnels, N.R. Div. Sect. K. (Bergen Hill Tunnels) Method of using Cross-Section Rod in getting Sections of Tunnel. Aug. 30, 06.
Fig. 3. K 115. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill Tunnels) Weehawken Shaft, North Tunnel Conveyor used by King Rice and Garney for handling and placing concrete. June 3, 07.
Fig. 4. K 116. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill Tunnels) Weehawken Shaft, North Tunnel. View of conveyor for placing concrete, with bucket suspended over hopper above belt. Steel forms in fore ground. June 4, 07.
[History.]—The contract for this work was let on March 6th, 1905, to the John Shields Construction Company; it was abandoned by the Receiver for that company on January 20th, 1906, and on March 20th, of that year, was re-let to William Bradley, who completed the work by December 31st, 1908.
The progress of excavation and lining in the North Tunnel is shown graphically on the progress diagram, [Fig. 9], that of the South Tunnel being practically the same.
[Geology.]—Starting west from the Weehawken Shaft, the tunnels pass through a wide fault for a distance of nearly 400 ft., this fault being a continuation of that which forms the valley between the detached mass of trap and sandstone known as King’s Bluff, which lies north of the tunnels, and the main trap ridge of Bergen Hill.
The broken ground of the fault, which consists of decomposed sandstone, shale, feldspar, calcite, etc., interspersed with masses of harder sandstone and baked shale, gradually merges into a compact granular sandstone, which, at a distance of 460 ft. from the shaft, was self-supporting, and did not require timbering, which, of course, had been necessary up to this point.
A full face of sandstone continued to Station 274 + 60, 940 ft. from the shaft, where the main overlying body of trap appeared in the heading. The full face of the tunnel was wholly in trap at about Station 275 + 30, and continued in this through to the Western Portal, where the top of the trap was slightly below the roof of the tunnel, with hardpan above. The contact between the sandstone and the overlying trap was very clearly defined, the angle of dip being approximately 17° 40' toward the northwest.
The sandstone and trap are of the Triassic Period, and the trap of this vicinity is more particularly classified as diabase.
The character of the trap rock varied considerably. At the contact, at Station 275, and for a distance of approximately 200 ft. west, corresponding to a thickness of about 60 ft. measured at right angles to the line of the contact, a very hard, fine-grained trap, almost black in color, was found, having a specific gravity of 2.98, and weighing 186 lb. per cu. ft. The hardness of this rock is attested by the fact that the average time required to drill a 10-ft. hole in the heading, with
a No. 34 slugger drill, with air at 90 lb. pressure, was almost 10 hours. The specific gravity of this rock is not as high as that of some other specimens of trap tested, which were much more easily drilled. This rock was very blocky, causing the drills to bind and stick badly, and, when being shoveled back from the heading, as it fell it sounded very much as though it were broken glass.
The remainder of the trap varied from this, through several changes of texture and color, due to different amounts of quartz and feldspar, to a very coarse-grained rock, closely resembling granite of a light color, though quite hard. The speed of drilling the normal trap in the heading was approximately 20 to 25 min. per ft., as compared with the 60 min. per ft. noted above, the larger amounts of quartz and feldspar accounting for the greater brittleness and consequently the easier drilling qualities of the rock. The normal trap in these tunnels has a specific gravity varying from 2.85 to 3.04, and weighs from 179 to 190 lb. per cu. ft.
The temperature of the tunnels, at points 1,000 ft. from the portals at both ends, remained nearly stationary, and approximately between 50° in winter and 60° in summer, up to the time the headings were holed through, being practically unaffected by daily changes in the temperature outside. At the western end, after the connection with the Central Shaft headings was made, there was almost always a current of air from the portal to the shaft, and ascending through the latter. This tended to make the temperature in this part of the tunnel correspond more nearly with the outside temperature; in fact, the variation was seldom more than 5° Fahr.
[Timbering.]—These tunnels have been excavated entirely by the center top heading method, almost invariably used in the United States. Timbering, where required, was of the usual segmental form with outside lagging, as shown in several of the photographs. In a few places it was necessary to hold the ground as the work progressed, and, in such cases, crown bars were used in the headings.
There was some little trouble at the Western Portal, where the top of the rock was very near the roof of the tunnel, as shown by Fig. 1, [Plate XXI]. A side heading was driven at the level of the springing line until a point was reached where the roof was self-supporting, and the timbering was brought out to the face of the portal from that point.
PLATE XXII.
TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1154.
LAVIS ON
PENNSYLVANIA R.R. TUNNELS: BERGEN HILL TUNNELS.
Fig. 1. K 26. P.R.R. Tunnels, N. R. D. Sect. K. (Bergen Hill Tunnels,) Weehawken Shaft. Scaffold car in South Tunnel at Sta. 267+60. Jan. 11, 06.
Fig. 2. K 31. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill Tunnels) Weehawken Shaft. Headhouse at ? elevator frame work, looking West. Oct. 17, 06.
Fig. 3.—Round Holes in Concrete Forms.
Fig. 4.—Round Holes in Concrete Forms Completed.
Drilling.—Where no timbering was required, several different methods were used in drilling and excavating the solid rock, though in all cases a center top heading was driven. The four diagrams, Figs. 1, 2, 3, and 4, give typical examples of these methods and show, in the order of their numbers, the general tendency of the development from a small heading kept some distance ahead of the bench, to a large heading with the bench kept close to it. The notes on each diagram give the general details of the quantity of drilling and powder used, methods of blasting, etc., and on the progress profile, [Fig. 6], is indicated those portions of the tunnels in which each method was used.
All the drills used throughout the work by Mr. Bradley were Rand No. 34 sluggers, with 3⅝-in. cylinders, and the steel was that known as the “Black Diamond Brand,” 1⅜-in., octagon. It was used in 2, 4, 6, 8, 10, and 12-ft. lengths; toward the end of the work it was proposed to use 14-ft. lengths, but owing to some delay in delivery this length was never obtained. The starters, 18 to 24 in. long, were sharpened to 2¾ to 3-in. gauge, which was generally held up to depths of 6 ft.; then the gauge gradually decreased until it was 1¾ to 2¼ in. at the bottom of a 12-ft. hole. Frequently, as many as three or four starters were used in starting a hole, and generally two sharpenings were required for each 2 ft. drilled, after the first 6 ft. It is estimated that about ¼ in. of steel was used for each sharpening, and that there was an average of one sharpening for every foot drilled.
The total quantity of steel used up, lost, or scrapped on the whole work was almost exactly 1 ft. for each 10 cu. yd. excavated, equal to 1¼ in. of steel per yard, distributed approximately as follows:
| Sharpening | ¾ to ⅞ in. | |
| Other losses | ½ to ⅜ ” | |
| Total | 1¼ in. per cu. yd. |
An “Ajax” drill sharpener was used, and proved very satisfactory. Rubber and cotton hose, covered with woven marlin, was used for the bench (3 in. inside diameter, in 50-ft. lengths), for drills (1 in. in diameter, in 25-ft. lengths), and for steam shovels (2½ in. in diameter, in 50-ft. lengths). Hose coverings of wound marlin, and of woven marlin with spiral steel wire covering were tried, but were not satisfactory, owing to the unwinding of the marlin and the bending of the steel covering.
Figures 1-4 were identically laid out; Figure 1 is representative. In the enlarged views, the plans have been rotated to match the longitudinal section. In the tables, variation between “to” and “-”, and formatting of table entries, is as in the original.
Adv.: Advance
Cu. Yd.: Cubic Yards
CROSS-SECTION
LONGITUDINAL SECTION
PLAN
| Per Round | Per Cubic Yard | Per linear Foot of Tunnel | |||||||
| Total Depth Drilled | No. of Cubic Yards | Pounds of Dynamite | Adv. | Linear Feet Drilled | Pounds of Dynamite | Cu. Yd. | Linear Feet Drilled | Pounds of Dynamite | |
| Heading | 140-155 | 18-21.6 | 93-131 | 5-6 | 8-9 | 5-6 | 3.6 | 29.-32 | 18-22 |
| Bench | 110-120 | 53-60 | 76-97 | 3½-4 | 2 | 1.4-1.6 | 15.4 | 30.-31 | 21.5-24.6 |
| Total | 19 | 59.63 | 39.5-46.6 | ||||||
| Per cubic yard, whole tunnel section | 3 to 33 | 2.1-2.5 | |||||||
| Blasting Notes: | Number of Sticks | |
| Heading: | First Round: 6 sticks, 60% in each cut hole, cut generallyblasted twice | 36 to 72 |
Second Round: 3 side holes each side, 5 sticks, 40%ea. | 30 | |
Third Round: Rest of side holes and dry holes, 5 sticks, 40%each | 40 | |
| Stub holes, say | 5 to 15 | |
| Total Sticks | 111 to 157 | |
| Total Pounds | 93 to 131 | |
Sub‑bench: | 4 widening holes; 2 to 3 sticks, each, 40% | 10 to 12 |
6 down holes; 5 to 7 sticks, each, 40% | 30 to 42 | |
| Bench: | 6 holes; 6 to 8 sticks each, 40% | 36 to 48 |
| Taking up bottom, average, say | 15 | |
| Total Sticks | 91 to 117 | |
| TotalPounds | 76 to 97 | |
CROSS-SECTION
LONGITUDINAL SECTION
PLAN
| Per Round | Per Cubic Yard | Per linear Foot of Tunnel | |||||||
| Total Depth Drilled | No. of Cubic Yards | Pounds of Dynamite | Adv. | Linear Feet Drilled | Pounds of Dynamite | Cu. Yd. | Linear Feet Drilled | Pounds of Dynamite | |
| Heading | 190-220 | 35-42 | 134-196 | 6½-8 | 5.4-6.0 | 3.9-5.0 | 5.3 | 28 to 32. | 20.7-26.5 |
| Bench | 110-130 | 55 | 79-106 | 4 | 2.-2.4 | 1.4-2.0 | 13.7 | 27.-33. | 19.2-27.4 |
| Total | 19 | 55.-65. | 39.9-53.9 | ||||||
| Per cubic yard, whole tunnel section | 2.9-3.4 | 2.1-2.8 | |||||||
| Blasting Notes: | Number of Sticks | |
| Heading: | First Round; 2 to 3 relieving holes sprung with 4 to 5 stickseach | 8 to 15 |
8 cut holes, 7 sticks each (sometimes shot twice) | 56 to 112 | |
First side round, 6 holes, 6 sticks each | 36 | |
Widening and dry holes, 10 to 12, 6 sticks each | 60 to 72 | |
| Total Sticks | 160 to 235 | |
| Total Pounds | 134 to 196 | |
Sub‑bench: | 8 holes, 4 to 6 sticks, each | 32 to 48 |
| Bench: | 8 holes, 6 to 8 sticks, each | 46 to 64 |
| Taking up bottom, average | 15 | |
| Total Sticks | 95 to 127 | |
| Total Pounds | 79 to 109 | |
CROSS-SECTION
LONGITUDINAL SECTION
PLAN
| Per Round | Per Cubic Yard | Per linear Foot of Tunnel | |||||||
| Total Depth Drilled | No. of Cubic Yards | Pounds of Dynamite | Adv. | Linear Feet Drilled | Pounds of Dynamite | Cu. Yd. | Linear Feet Drilled | Pounds of Dynamite | |
| Heading | 190 to 220 | 35 to 42 | 134 to 196 | 6½ to 8 | 5.4 to 6.0 | 3.9 to 5.0 | 5.3 | 28 to 32 | 20.7 to 26.5 |
| Bench | 145 ” 190 | 90 to 110 | 118 ” 167 | 6½ ” 8 | 1.6 ” 1.9 | 1.3 ” 1.8 | 13.7 | 22 ” 36 | 17.8 ” 24.7 |
| Total | 19 | 50 ” 58 | 38.5 ” 51.2 | ||||||
| Per cubic yard, whole tunnel section | 2.6 ” 3.1 | 2.0 ” 2.6 | |||||||
| Blasting Notes: | Number of Sticks | |
| Heading: | First Round: 2 to 3 relieving holes sprung, with 4 to 5 stickseach | 8 to 15 |
8 cut holes, 7 sticks each (sometimes shot twice) | 56 to 112 | |
First side round, 6 holes, 6 sticks each | 36 | |
Widening and dry holes, 10 to 12 holes, 6 stickseach | 60 to 72 | |
| Total Sticks | 160 to 235 | |
| Total Pounds | 134 to 196 | |
Sub‑bench: | 4 widening holes, 4 to 5 sticks each, 2 rounds | 32 to 40 |
6 down holes, 5 to 7 sticks each, 2 rounds | 60 to 84 | |
| Bench: | 4 down holes, 5 to 7 sticks each | 20 to 28 |
6 to 8 lift holes, 5 to 6 sticks each | 30 to 48 | |
| Total Sticks | 142 to 200 | |
| Total Pounds | 118 to 167 | |
CROSS-SECTION
LONGITUDINAL SECTION
PLAN
| Per Round | Per Cubic Yard | Per linear Foot of Tunnel | |||||||
| Total Depth Drilled | No. of Cubic Yards | Pounds of Dynamite | Adv. | Linear Feet Drilled | Pounds of Dynamite | Cu. Yd. | Linear Feet Drilled | Pounds of Dynamite | |
| Heading | 310-320 | 63-71 | 215-257 | 8-9 | 4.5-5.1 | 3.4-5.7 | 7.9 | 35.6-45. | 26.9-45.0 |
| Bench | 190-210 | 89-100 | 107-155 | 8-9 | 1.9-2.2 | 1.2-1.7 | 11.1 | 21.1-24. | 13.3-18.9 |
| Total | 19 | 56.7-69. | 40.2-63.9 | ||||||
| Per cubic yard, whole tunnel section | 3.-3.6 | 2.1-3.4 | |||||||
| Blasting Notes: All holes of whole round are cleaned and loaded before blasting isstarted | Number of Sticks | |
| First Round: | 5-6 lift holes, 7 to 9 sticks each | 35 to 54 |
First row, sub-bench, 6 holes, 6 to 8 sticks each | 36 to 48 | |
| Second Round: | Second row, sub-bench and widening holes, 8 to 10 holes,6 to 8 sticks each | 48 to 64 |
| Stub holes | 10 to 20 | |
Bench: Total Sticks | 129 to 186 | |
| Total Pounds | 107 to 155 | |
| Third Round: | 8 cut holes, 7 sticks each, often requires 3 to 4charges | 112 to 224 |
| Fourth Round: | 8 holes, First side round, 5 to 7 sticks each | 40 to 56 |
| Fifth Round: | 8 holes, Second side round, 5 to 7 sticks each | 40 to 56 |
2 dry holes 5 to 7 sticks each | 10 to 14 | |
| Sixth Round: | 4 to 6 widening holes and dry holes, 6 sticks each | 36 to 48 |
Stub holes | 20 to 30 | |
Heading: Total Sticks | 258 to 428 | |
| Total Pounds | 215 to 357 | |
The average quantity of powder used on the whole work was about 2.9 lb. per cu. yd. The tables on the diagrams, Figs. 1, 2, 3, and 4, show that the quantity actually used in making the advance at the main working faces was about 2.5 lb. The difference is accounted for by the larger percentage of powder used for trimming the sides, breaking out the cross-passages between the tunnels, and the excavation of the ditches, the latter operation not being done until the concrete lining was about to be put in.
There was some time, too, during the earlier stages of the work, when it is believed that an excessive quantity of powder was used; for one or two months it ran up to 4 lb. per cu. yd.
MUCK CAR USED AT WEEHAWKEN SHAFT
The dynamite used was “Forcite.” At first, both 40% and 60% were used, the 60% generally only for blasting the cut in the headings; during the latter part of the work, however, the 60% was used exclusively.
The rock as a rule broke very well, and only a comparatively small quantity could not be handled by the shovels without being broken up further by block-holing. In the sandstone the quantity of powder per cubic yard was much more than for any of the trap.
In drilling the Central Shaft, a 6-hole cut was made approximately on the center line, east and west, the enlargement requiring about 18 more holes, which were generally about 6 ft. deep, the average advance being about 4 ft. per day of 24 hours.
NORTH TUNNEL
[larger view]
SOUTH TUNNEL
[larger view]
PROGRESS PROFILES OF NORTH AND SOUTH TUNNELS SHOWING MONTHLY EXCAVATION
The drills were run by steam until a depth of about 150 ft. had been reached, air from the plant at Hackensack being available after
that time. Four drills were used most of the time, and six later when air was available. This work was done entirely by the John Shields Construction Company, and a depth of 205 ft. was sunk in 6 months (from July 15th, 1905, to January 15th, 1906). A derrick was used for hoisting and lowering men and tools during the sinking, elevators being put in later.
PLATE XXIII.
TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1154.
LAVIS ON
PENNSYLVANIA R.R. TUNNELS: BERGEN HILL TUNNELS.
[Drilling Data.]—During the progress of the work, both general and detailed observations were made of the drilling, the results of which are shown in the tables. Table 1 has been compiled from the records as platted daily on the chart from the inspectors’ reports, as shown by Plate XXIII, and described on [page 113]. Table 2 contains some data relating to the drilling in the headings.
The general results of these observations show that the average time the drills were “actually working” was 5.2 hours per shift, and that they were actually “hitting the rock” about half of this time, or about 2.5 hours per shift. The average depth drilled per hour, during the time the drills were “actually working,” was 2.66 ft.
The “actual working time,” as noted above, covers the period from the time the drills were first set up in the heading after blasting until they were taken down for the next blast; it does not include the time occupied in setting up or taking down, which would probably average 30 min. more per shift. It is believed that this figure will also apply very closely to drills working on the bench, though no actual observations were taken to determine this, on account of the irregularity with which they were worked.
The actual working time of the drills in the 736 shifts (7,360 hours) covered by Table 1, was 3,826 hours, or 5.2 hours per shift. The average depth drilled per yard, as shown in the last column of Table 1, agrees fairly well with the figures on the diagrams, Figs. 1, 2, 3, and 4.
Table 2 has been compiled from detailed timed observations of individual drilling of down holes in the bench, for periods of 7 or 8 hours each, in January, 1907. The work at that time was in fairly normal condition at all points.
The figures in the third column of Table 2 include the time required for moving from one hole to another, when this occurred during the observation, the time required for changing bits, oiling drills, etc., and all delays of all kinds. A close record of the delays was
kept, and it was considered that, of the 93 hours, 48 min., in Table 2, the unnecessary delays amounted to 5 hours, 7 min., or about 5½ per cent.
[TABLE 1.]
| Shifts: Number of shifts covered by observations. Hours: Average number of hours worked per shift. D/Hr: Average depth drilled per hour per drill D/Yd: Average depth drilled per yard. | Hack.: Hackensack Whk.: Weehawken CS: Central Shaft |
| Method. | Date. | Shifts | Place. | Hours | D/Hr | D/Yd | |
No. 1— | Aug. ’06 | 44 | Hack., | N. | 5.69 | 2.78 | 10.1 |
| Sept. ’06 | 38 | ” | N. | 5.80 | 3.77 | 11.1 | |
| Aug. ’06 | 43 | ” | S. | 5.60 | 2.89 | 9.1 | |
| Sept. ’06 | 36 | ” | S. | 6.18 | 2.65 | 8.7 | |
| Jan. ’07 | 16 | CS E. | N. | 5.99 | 2.99 | 8.2 | |
| Jan. ’07 | 20 | ” | S. | 6.05 | 2.9 | 7.1 | |
| Apr. ’07 | 48 | CS W. | N. | 4.92 | 3.3 | 6.7 | |
| Apr. ’07 | 48 | ” | S. | 5.00 | 3.2 | 7.7 | |
Nos. 2 and 3— | Dec. ’06 | 54 | Whk., | N. | 4.95 | 2.16 | 4.52 |
| Dec. ’06 | 54 | ” | S. | 5.23 | 2.14 | 4.54 | |
| Dec. ’06 | 52 | Hack., | N. | 5.03 | 2.2 | 5.77 | |
| Dec. ’06 | 54 | ” | S. | 5.90 | 1.82 | 5.67 | |
No. 4— | June ’07 | 56 | Whk., | N. | 4.77 | 2.55 | 4.23 |
| June ’07 | 58 | ” | S. | 4.82 | 2.26 | 3.88 | |
| May ’07 | 60 | Hack., | N. | 4.67 | 2.44 | 5.00 |
| May ’07 | 60 | ” | S. | 4.54 | 2.57 | 4.80 | |
[TABLE 2.]
| Date. | Place. | Total working time. | Number of feet drilled. | ||
| Hours. | Minutes. | ||||
| Jan. 14th, 1907 | Weehawken | N. | 8 | 0 | 15 |
| ” 15th, 1907 | ” | N. | 7 | 32 | 12 |
| ” | N. | 7 | 22 | 14 | |
| ” 12th, 1907 | ” | S. | 8 | 0 | 20 |
| ” | S. | 8 | 0 | 11 | |
| ” | S. | 8 | 0 | 10 | |
| ” 11th, 1907 | Hackensack | N. | 8 | 0 | 13 |
| ” 17th, 1907 | ” | N. | 7 | 10 | 10 |
| ” | N. | 7 | 5 | 11 | |
| ” | N. | 7 | 10 | 10 | |
| ” 16th, 1907 | ” | S. | 4 | 20 | 10 |
| ” | S. | 6 | 9 | 10 | |
| ” | S. | 7 | ... | 8 | |
| Totals. | 93 | 48 | 154 | ||
Average: 36.6 min. per ft. drilled, or 1.64 ft. drilled per hour.
As a check on the average figures obtained from various sources, the following estimate of the cost of drilling per cubic yard was made up from these average figures, for comparison with the actual average cost on the whole work. The cost records show this to be about $2.25 per yd., exclusive of power for running the drills, almost exactly what
the following estimates give for theoretical average conditions, although no effort was made to have this latter compare so closely.
Estimated Cost per Drill per Day.
| Drill Runner | 1 | at $3.50 per day, | $3.50 |
| Helper | 1 | ” 2.00 ” ” | 2.00 |
| Nipper | 1/5 | ” 1.75 ” ” | 0.35 |
| Heading foreman | 1/12 | ” 5.00 ” ” | 0.42 |
| Walking boss | 1/50 | ” 7.50 ” ” | 0.15 |
| Blacksmith | 1/12 | ” 4.00 ” ” | 0.34 |
| Blacksmith helper | 1/12 | ” 2.00 ” ” | 0.16 |
| Machinist | 1/12 | ” 3.00 ” ” | 0.25 |
| Machinist helper | 1/24 | ” 1.75 ” ” | 0.07 |
| Pipe fitter and helper | 1/50 | ” 5.00 ” ” | 0.10 |
| Oil, waste, blacksmith coal, etc. | 0.24 | ||
| Drill steel, 6 in. per shift | 0.20 | ||
| $7.78 |
| Average number of feet drilled per cubic yard | 3 to 3.5 |
| Number of feet drilled per drill, per shift | 10.5 to 12 |
| Number of yards per drill, per shift | 3.5± |
| Cost of drilling, per yard, $7.78/3.5 | $2.22± |
In all the foregoing tables and computations, the quantities used have been those paid for. The quantity taken out, however, has been 10% more than that paid for, and 28% more than the contractor was actually required to take out.
The specifications required that the excavation should be taken entirely outside of the neat line, as shown on Plate VIII of the paper by Mr. Jacobs, but not necessarily beyond this line, but that the contractor would be paid for rock out to the standard section line, which is 1 ft. larger on the sides and top and 6 in. deeper in the bottom than the neat line.
A great deal of the extra quantity was due to rock falling from the core-wall side whenever one working face was behind the other. Blasting at the face behind generally loosened more or less rock on the core-wall side of the tunnel which was ahead, in one or two instances breaking entirely through, as shown in Fig. 2, [Plate XXVI], the hole in the core-wall in this case being utilized by building a storage chamber in it.
Table 3 gives some of the statistics of drilling in the Simplon Tunnel, as compared with the drilling on this work, the figures for the Simplon being taken from papers read before the Institution of Civil Engineers of Great Britain.
[TABLE 3.]
| Bergen Hill. | Simplon. | |
| Drills set up in heading, percentage of total elapsed time | 50% | 60% |
| Actually drilling the rock, percentage of total elapsed time | 25% | 50% |
| Average advance per round (attack) | 8.5 ft. | 3.8 ft. |
| Average time for each attack | 36 hours. | 5 hours. |
| Average advance per day of 24 hours | 5 ft. | 18 ft.† |
| Depth of holes | 10 ft. | 4.6 ft. |
| Diameter of holes | 2¾ in. | 2¾ in. |
| Linear feet drilled per hour, per drill | 2.7 | 7.0 |
| Linear feet drilled per cubic yard | 5.0 | 6.0 |
| Pounds of dynamite per cubic yard | 3.4 to 5.7 | 8½ |
| Average depth drilled with one sharpening | 12 in. | 6½ in. |
| Total number of men per day of 24 hours* | 450 | 3,300 |
* On Bergen Hill Tunnels, for two full working faces at the Hackensack end, about 3,000 ft. in from portal (March, 1908). At Simplon, two full faces and two headings, at a distance of about 5,000 ft. in from the portal (January, 1900). These both include lining as well as excavation. The lining of the Bergen Hill Tunnels progressed about twice as fast as the excavation; it is inferred that on the Simplon it progressed at about the same rate as the excavation.
† At the Italian end, in Antigoric gneiss, which is stated to be very hard rock.
The figures in Table 3 are for “heading only” in both cases, except for the last item (number of men), the heading in the Simplon Tunnels being about 60 sq. ft., as compared with the heading of Method No 4 (which has been used for comparison), of 210 sq. ft.
[Mucking and Disposal.]—The conditions affecting the disposal of the muck, after blasting, were quite different at the two ends, the grade descending in the direction of the loads at Weehawken and ascending at the Hackensack end. At the Weehawken end the mouth of the tunnels was at the bottom of a shaft some 80 ft. deep, Fig. 2, [Plate XXII], the muck in the tunnel cars being hoisted by elevators to a platform at the top from which it was dumped into standard-gauge cars supplied by the Erie Railroad, as shown by [Fig. 7]; or later hauled to the crusher or storage pile, some 500 ft. distant, on the north side of Baldwin Avenue. At the western end, the cars were hauled directly to the surface through the approach cut, and the material, except that required for concrete and rock packing, was deposited in the embankment across the Hackensack Meadows, a haul of from 1,000 to 3,000 ft. beyond the portal.
All disposal tracks were of 3-ft. gauge, the main running tracks being generally laid with 60-lb. second-hand rails, although some of lighter weight were used.
Except for about 1,000 ft. in each tunnel at the Weehawken end, where the muck was loaded by hand, four steam shovels, operated by compressed air, were used, one at each working face. One of these was a “Marion, Model No. 20,” weighing 38 tons, the others were “Vulcan Little Giant,” of about 30 tons each. All these shovels were on standard-gauge track, and were moved back from 300 to 500 ft. from the working face during blasting.
METHOD OF EMPTYING DUMP CARS AT WEEHAWKEN SHAFT
At Weehawken, previous to the time the shovels were installed, the muck was shoveled by hand into the cars from the bottom of the bench, and the heading muck was dumped into them from the movable platform (Jumbo) shown by Fig. 1, [Plate XXII]. There were three loading tracks at the face. The cars used at that time were similar to that shown by [Fig. 5], but were about two-thirds the size and had no end door; stop-planks were supposed to be placed in the ends but seldom were. The loads averaged about ½ cu. yd. (measured in place). After the shovel was installed the cars shown by Fig. 5 were used, and the loads averaged nearly 1 cu. yd.
The empty cars were pushed up to the shovel by hand from the storage track. When loaded, they were given a start with the bucket of the shovel, and were then allowed to coast by gravity out to the storage track near the shaft, where they were stopped by placing rolls of cement bags or burlap on the rails. After the lining was started, the loaded cars were stopped on the inside of the lining and only sent out over the single track through this latter at stated intervals,
when several cars followed in close succession, with a long interval which permitted the concrete to be brought in. The empty cars were hauled back to the storage track near the working face by mules, one mule usually hauling two cars at a time.
Up to the time the trap rock was reached, about 1,100 ft. from the shaft, the excavated material was disposed of by loading it on flat cars. All the trap, however, was stored to be used later for concrete and ballast.
When the tunnels were in full working order, sixty muck cars of the type shown by [Fig. 5], were in use, about evenly divided between the two tunnels. For some time the work was greatly hampered by lack of cars, and even with the sixty finally obtained, there were many times when extra cars could have been used to advantage to keep the shovel working.
When mucking by hand, the mucking gangs consisted of from 15 to 20 men. The maximum output was 50 cu. yd., and averaged about 35 cu. yd. per shift; there was a great deal of trouble in keeping the gangs full, as labor at that time was very scarce, and the tunnels were quite wet. The maximum output of either of the shovels was 159 cu. yd. in one shift, and the best average in any month—which was between July and December, 1907, during which time only the enlargement and bench of the Central Shaft headings was being taken out from the western end—was 60 cu. yd. per shift. As the shovels were generally idle for one shift out of three, the quantity actually handled averaged 90 cu. yd. per shift during the shifts the shovel worked. All these quantities were “measured in place,” and, as previously noted, would be about equal to twice as much measured loose in the cars.
The shovels at both ends were usually worked with three crews for the two tunnels; two day crews, one at each shovel, and a night crew which was used in either tunnel as occasion required. The day crews generally averaged from 45 to 60 hours overtime during the month, one of them working during the early part of the evenings in the opposite tunnel to the night crew. For a short time, when the ventilation at the western end was very bad, four crews were worked, day and night crews in each tunnel; but, as a general rule, the method of working three crews was preferred by the men, and was less expensive for the contractor.
At the Hackensack end, 4-yd., Allison, one-way, dump cars were used, being handled by “dinky” locomotives, of which there were three in use up to October, 1907, and four after that. One 15-ton Porter engine, with 10 by 16-in. cylinders, was used outside the tunnels for handling the trains (from 6 to 8 cars) on the dumps and to the crusher; the other three, 12-ton Vulcans, 9 by 14-in., were used in the tunnels. About 30 dump cars were in use, and of these there were generally from 3 to 6 under repair.
Generally, 4 cars were hauled out together, although 5 and occasionally 6 were handled. The work was generally arranged so that the heavy mucking shift alternated in the two tunnels, the two engines being worked there and a single engine in the other tunnel.
The tunnel engines left the cars on a track just outside the portal, from which they were made up into trains of from 6 to 8 cars and taken to the dump or crusher by the large “dinky.”
The muck from the Central Shaft headings was loaded by hand into cars similar to that shown by [Fig. 5], but smaller and having no door at the forward end. A double elevator took the cars to a platform about 20 ft. above the surface, where they were dumped by revolving platforms, similar to those at Weehawken, into storage bins or directly into wagons. The muck was all hauled away in wagons; part of it was used to fill some vacant lots, and part was hauled to the crusher at the Western Portal.
The method under which the best results were obtained was that in which a full round was blasted every 36 hours, securing an advance of practically 9 ft. of full section. During the first shift of the three, as soon as the blasting had been completed and lights strung, the shovel was moved forward, and cleaned up the floor to the main pile of muck, the material from the blast being scattered from 150 to 300 ft. back from the face; during this shift, also, the drillers mucked the heading and set up their drills, the muckers helping to carry in the columns and drills. During the second shift the main pile of muck was disposed of, leaving not more than 2 or 3 hours’ work for the shovel on the third shift. This left nearly the whole of the third shift for drilling the lift holes.
[Ventilation.]—At Weehawken considerable difficulty was caused by fog and smoke accumulating in the tunnels after blasting. This was generally worse on days when the barometric pressure was low outside,
and worse in the North than in the South Tunnel. A 6-ft. fan, driven by an electric motor, was installed in the cross-passage at Station 274, 900 ft. from the shaft, the headings at that time being about 300 ft. in advance of this point, to force the air from the South into the North Tunnel, drawing it in at the mouth of the South Tunnel and discharging it at the mouth of the North Tunnel, thus insuring a circulation in both tunnels, as shown in plan by [Fig. 8].
This necessitated, of course, that the cross-passages between that in which the fan was placed and the mouths of the tunnels should be blocked tight. There was some difficulty in keeping this blocking tight, owing to the force of the blasting blowing out the bulkheads. The fan, however, did good service when it and the bulkheads were in good order. The compressed air discharged from the drills kept the headings fairly clear, as well as that part of the tunnel between the headings and the fan. The fan was moved ahead to the next cross-passage at Station 277 when the work had progressed far enough, and was used there for some time; it was found, however, that by the time the excavation had reached Station 280, about 1,500 ft. from the shaft, there was practically no further difficulty from fog and smoke. No satisfactory explanation was found for this, as it would rather be expected that the ventilation and trouble with smoke and fumes from blasting would be worse as the distance increased between the mouth of the tunnel and the working face. One explanation was offered: That the blasting of the softer sandstone tended to create more and lighter dust than the heavier trap rock; whether or not this was so, it is a fact that there was far less trouble with fog and smoke after the sandstone was passed.
At Hackensack, the principal cause of trouble was the smoke from the “dinky” locomotives. As the tunnels progressed, this gradually became worse, until a connection was made with the Central Shaft headings. A fan was installed in the cross-passage at Station
316 (700 ft. in from the portal), but was never worked properly. Apparently, the men, at least the walking bosses and foremen, had little faith in the fan as a means of ventilation; no real attempt was made to keep it in order or operate it properly, and a great deal of time and money was lost groping around in the smoke and fog, the density of which increased, not only with the state of the atmosphere, but also with the direction of the wind. On some days the tunnels easily cleared themselves, and on others the smoke was so thick that a candle held at arm’s length could not be seen. At this end, the South Tunnel was generally worse than the North. After the headings were holed through between the portal and the Central Shaft there was very little trouble, there being usually a strong up-draft through the shaft. This was so pronounced when the wind was blowing toward the portal, that the moisture-laden air, as it ascended from the mouth of the shaft, presented the appearance of a heavy rainstorm with the rain ascending instead of descending. When the wind was blowing away from the portal, that is, from the southeast, the effect of the shaft as a chimney was neutralized, and, consequently, the smoke accumulated in the tunnels. To overcome this, a large blower, with a fan 9 ft. in diameter, and with blades 4 ft. wide and 2 ft. 3 in. long, operated by a vertical 12-h.p. engine, was installed at the top of the shaft, and this kept the tunnels reasonably clear of smoke at all times. After the bench and enlargement had passed the bottom of the shaft, the use of the fan was abandoned, as it was found that the tunnels cleared themselves fairly well, probably owing to the larger cross-section reaching all the way to the Shaft. What little fog and smoke there might be did not cause enough trouble to warrant the cost of running the fan, which, owing to its location, required the whole time of a mechanic in attendance day and night.
[Lighting.]—During the earlier stages of the work, gasoline lamps and Kitson lights were used. The former, of the familiar banjo type, and a modification of this, with a section of wrought-iron pipe for the reservoir, were very unsatisfactory, and were out of repair and leaking a large proportion of the time. The Kitson lights were given only a short trial, but were found unsatisfactory, owing to the necessity of moving them frequently and having to set them up in insecure positions. Electric lights were installed by Mr. Bradley, on his assumption of the contract.
The number of lamps maintained in each of the tunnels for the excavation was approximately as follows:
| At the main working face | From 8 to 10 |
| On and around the shovel | ” 9 to 12 |
| Between the portal and the working face | ” 60 to 80 |
The cost of lighting for the whole work averaged about 15 cents per cu. yd., which is quite large. This was mainly due to the fact that current was bought from outside sources during a large part of the time (one-third of the yardage). Part of this current cost 5 cents per kw-hr., and there were fairly heavy charges for connecting the tunnel wiring system with the source of supply. Current bought from the Public Service Corporation cost from 10 to 12 cents per kw-hr. delivered at the mouth of the tunnel.
[Pumping.]—The quantity of water encountered during the excavation of the tunnels, measured somewhat roughly, was approximately as follows:
| At Weehawken | 74 gal. per min. |
| At Central Shaft | 1 ” ” ” |
| At Hackensack | 18 ” ” ” |
The water at the Weehawken end had to be pumped from the bottom of the shaft, a lift of about 90 ft., while at the Hackensack end it had to be pumped back from the face up grade to the portal.
The cost of pumping was about $100 to $125 per month for labor for the whole work, besides the cost of the plant (about $1,200) and the power for running it.
[Progress.]
The total time elapsed from the time of starting work at the Weehawken end, in May, 1905, to the completion of the excavation, in May, 1908, was almost exactly three years. Of this time about 40 days were lost in February and March, 1906, when work was stopped by the Receiver of the Shields Company, the total number of days actually worked being about 940, giving an average progress of 6.26 ft. per working day in each of the two tunnels, which, omitting the Central Shaft headings, gives an average rate of progress for each working face, of 3.13 ft. per day.
These 940 days include practically all the time elapsed, except Sundays and such few holidays as were observed. For some of this time, work was being carried on at only one or two points; the time, therefore, represents practically the total possible working time during the period covered.
[Progress at Weehawken.]—At Weehawken the total number of days worked was 763, divided as follows:
186 days in timbered section, about 426 ft., an average rate of 2.3 ft. per day in each tunnel;
176 days in hard sandstone, about 563 ft., an average rate of 3.2 ft. per day in each tunnel;
112 days in hard trap, about 267 ft., an average rate of 2.4 ft. per day in each tunnel;
289 days in ordinary trap, about 1,316 ft., an average rate of 4.55 ft. per day in each tunnel.
[Progress at Central Shaft.]—At Central Shaft the average length driven per day in each of the four headings is shown by Table 4.
[TABLE 4.]
| Location. | Number of days worked. | Total length of heading, in feet. | Average length of heading driven per day worked, in feet. |
| N.E. | 227 | 446 | 1.96 |
| S.E. | 168 | 346 | 2.06 |
| N.W. | 272 | 768 | 2.82 |
| S.W. | 234 | 698 | 2.98 |
[Progress at Hackensack.]—At Hackensack the total number of days worked on the tunnels proper, all in trap rock (omitting the cut and cover) was about 792, divided as shown in Table 5.
[TABLE 5.]
| Location. | Number of days worked. | Advance. | Average advnce per day. |
| Station 323 to Central Shaft headings | 492 | 1,450 | 4.5 |
| Bench and enlargement of Central Shaft headings | 159 |
{1,150* { 906† |
7.2* 5.7† |
| Central Shaft headings to Weehawken headings | 141 | 620 | 4.4 |
* Actual advance.
† Equivalent linear feet of full section tunnel.
The best month’s work in each location was as follows, the actual yardage excavated and paid for being reduced to equivalent linear feet of full section. The tunnels were generally taken out to full section, except for a small amount left in the bottom, which latter reduced the equivalent linear feet of full section to about 95% of the actual advance at the face.
Weehawken.—
| Linear feet. | Feet per day. | |||
| Full timbered section, | North Tunnel | Nov., 1905, | 87 == 3.0 | |
| Sandstone | ” ” | May, 1906, | 109 == 3.9 | |
| Trap (normal) | South ” | July, 1907, | 144 == 5.3 | |
Hackensack (All trap).—
| Linear feet. | Feet per day. | |||
Portal to Central Shaft headings, | South Tunnel | May, 1907, | 139 == 5.0 | |
* Enlargement of headings, | ” ” | Nov., 1907, | 175 == 6.0 | |
Central Shaft headings to Weehawken headings, | Apr., 1908, | 145 == 5.2 | ||
* The actual advance of the bench this month was 202 lin. ft.
[Central Shaft Headings.]—During April, 1907, 122 lin. ft. of heading, averaging 3.8 cu. yd. per lin. ft., were taken out in the South Tunnel, west of the shaft. This was equal to 5.0 ft. per day for the 24 days worked.
[The Best Week’s Work.]—The best week’s work at either of the main working faces, when the full section was being excavated in trap rock, was 803 cu. yd., equal to 41.8 lin. ft. of full-section tunnel, or an average of 6.0 lin. ft. of full section per day; this was from the South Tunnel at Hackensack for the week ending January 11th, 1908.
[The Best Yardage.]—The largest number of yards taken out in any one week from one working face was 1,087, equivalent to 56.6 lin. ft. of full section, or an average of 8.1 lin. ft. of full section per day. This was bench and enlargement only (Central Shaft headings) in the North Tunnel, Hackensack, for the week ending October 19th, 1907.
The largest yardage for the whole work in any one week was 3,238 cu. yd. from four working faces—two at Weehawken in full section and
two at the Hackensack bench and enlargement (Central Shaft headings). This was equivalent to 168.4 lin. ft. of full-section tunnel, or an average of 6 ft. per day from each working face.
[The Best Month’s Work.]—The best month’s work with each of the four methods of drilling the headings, as shown in Figs. 1, 2, 3, and 4, where the work was straight forward and the full section was being taken out, was as follows:
| Method | No. 1 | About | 90 ft. in sandstone. | |
| ” | No. 2 | ” | 100 ” in trap. | |
| ” | No. 3 | ” | 137 ” in trap. | |
| ” | No. 4 | ” | 145 ” in trap. |
In regard to these figures it should be noted, as stated previously, that the organization of the men and plant was not properly completed until near the time Method No. 4 was put in operation.
In [Fig. 9] is shown graphically the relation of the progress to the time elapsed in the North Tunnel, the diagram for the South Tunnel being almost exactly the same.
PROGRESS PROFILE—NORTH TUNNEL
[Plant.]
The plant installed by the John Shields Construction Company, and taken over by Mr. Bradley, was composed very largely of second-hand material, and eventually most of it had to be replaced. Insufficient and inefficient plant and delay in installation were largely responsible for the small progress made by the Shields Company, and Mr. Bradley’s endeavor to utilize this plant not only caused much delay during the first 8 or 10 months after he started work, but also involved large expense.
[Power Plant.]—At Weehawken the plant installed by the Shields Company consisted of three old locomotive boilers, each having a nominal capacity of about 125 h.p., and one Rand and one Ingersoll-Sergeant compressor, each of a rated capacity of about 1,250 cu. ft. of free air per min. compressed to 100 lb.
To this Mr. Bradley added two more second-hand locomotive boilers, and another Rand compressor of the same type and capacity as the first. The theoretical steam capacity of each of the five old locomotive boilers was about 4,250 lb. per hour, or a total capacity of 21,250 lb. per hour.
Theoretically, the demand on this steam was:
| Pounds per hour. | ||
| Three compressors, about 5,600 lb. per hour each | 16,800 | |
| One dynamo | About | 1,000 |
| One 500-gal. pump | ” | 1,000 |
| One hoisting engine for elevators | ” | 2,000 |
| Total | 20,800 | |
Actually, there was considerable deficiency of steam when an endeavor was made to work the three compressors at their full capacity. A separate boiler was afterward installed to run the hoisting engine for the elevators and the pumps, thus leaving a requirement of only approximately 18,000 lb. of steam per hour, but even this was beyond the capacity of the boilers, especially as one was almost always out of commission.
The two Rand compressors were 24 by 24 by 30-in., straight-line, one-stage, steam-driven, with a nominal capacity of 1,250 cu. ft. of free air per min. at 80 rev. per min. The Ingersoll-Sergeant was of similar type and capacity. Therefore, the theoretical quantity available was 3,750 cu. ft. of free air per min.
The theoretical air requirements (as taken from manufacturers’ catalogues) were:
|
Cubic feet of free air per minute. |
|
| 20 Rand slugger drills (12 by 174) | 2,088 |
| 2 Little Giant shovels (taking air two-thirds of the time) | 1,100 |
| Total | 3,188 |
This estimate, based on the assumption (given in the catalogues) that the drills would be working about three-fifths of the time, and the shovels about two-thirds of the time, left apparently an ample margin between the full capacity of the compressors and the requirements for the drills; as a matter of fact, however, it was seldom that more than 80 lb. of air was available, and the pressure often dropped to 60 or 50 lb. at the compressors. During the time this plant was in use the greatest distance to the drills was about 1,500 ft.
As this plant proved to be entirely inadequate to the demands, an arrangement was made with the O’Rourke Construction Company on
August 17th, 1906, whereby they agreed to supplement the air supply by 1,000 cu. ft. of free air per min. at 100 lb. pressure. This arrangement was not altogether satisfactory, and finally (on December 5th, 1906) an arrangement was made with the same company to supply air up to 4,000 cu. ft. of free air per min. at 100 lb., and the old plant was shut down.
The new plant had been in use previously in the construction of the River Tunnels. The air from it was compressed to 40 lb. by low-pressure machines, one being used all the time and two when necessary. These machines were built by the Ingersoll-Sergeant Company, the engines being of the Corliss duplex type, cross-compound steam, with simple duplex air cylinders, each compressor having a capacity of nearly 4,000 cu. ft. of free air per min. This air, at 40 lb., was delivered to an Ingersoll-Sergeant high-pressure machine, having Corliss cross-compound engines, 14 by 26 by 36-in., with air cylinders of the piston inlet type, 13¼ by 36-in., which compressed it to 100 lb. The capacity of this latter machine, taking air at normal pressure, is 920 cu. ft. of free air per min. working at 85 rev. per min.; by taking the air at 40 lb., and working at a somewhat higher speed, this machine alone supplied all the air used at the Weehawken end (approximately 4,000 ft.) from December, 1906, to November, 1907, and, with very few exceptions, the pressure was steadily maintained at from 90 to 100 lb., there being no break-down of any kind.
At Hackensack the plant taken over by Mr. Bradley consisted of six old locomotive boilers and four Rand compressors, all of the same type as those at Weehawken. To this he added two second-hand marine boilers, each of a stated capacity of about 350 h.p., and two more Rand compressors of the same type and capacity as the others, making the total theoretical steam power available approximately 1,450 h.p., with a compressor capacity of approximately 7,500 cu. ft. of free air per min., equal to about 1,500 h.p., allowing for 15% of loss.
Nowhere near the theoretical steam power was ever developed from the boilers. The tubes of the old locomotive boilers were filled with mud in many cases, and were always leaking. The marine boilers were not properly installed to give the best results, and it was seldom possible to work more than four compressors at once, or to keep the air pressure at the power-house much greater than from 70 to 80 lb. at any time.
This plant had been built by the Shields Company on the meadows alongside the Erie and New York, Susquehanna and Western Railroads, and the foundations were not made sufficiently strong to resist the effect of the vibration caused by the passing trains. It was impossible to keep the steam connections tight, and there was not only the loss of steam due to leaky joints, but positive danger of one of the main steam lines breaking entirely. After attempting to operate this plant for nearly 5 months, Mr. Bradley determined to abandon the site and the boilers, and build a new plant, farther back from the railroad, on solid ground, in such a position that a spur track could be built to a coal trestle in front of the boilers.
Two pairs of Stirling boilers, with a total capacity of 2,000 h.p., were installed. As a rule, at times of maximum demand, three of the boilers were in use; after the Central Shaft was stopped, two were generally sufficient, until, toward the latter part of the excavation, the losses in the transmission of the air made it necessary to keep three going.
Eight compressors (the six old ones with two brought from Weehawken), were installed in the new power-house. All were of the same type, namely, Rand, straight-line, steam-driven, 24 by 24 by 30-in., each with a nominal capacity of 1,250 cu. ft. of free air per min. Seven of these were generally worked to their full capacity in order to keep up the necessary supply of air.
The maximum requirements of air at this end were primarily estimated as follows:
| Central Shaft, four headings | 24 drills. |
| Hackensack, two working faces | 20 drills. |
| Total | 44 drills. |
|
Cubic feet of free air per minute. |
||
| 44 | Slugger drills (25 by 174) require | 4,350 |
| 2 | Steam shovels | 1,600 |
| Pumps and machine-shop, say | 1,000 | |
| 4 | Hoisting engines, placing concrete | 2,000 |
| 4 | Derricks | 2,000 |
| Total | 10,950 |
The theoretical capacity of the whole eight compressors was:
1250 × 8 = 10,000 cu. ft. of free air per min.
It was considered that not more than two-thirds of the above equipment would be working at the same time; the actual requirement, therefore, was taken at about 8,000 cu. ft. of free air per min., thus leaving a margin of one spare compressor.
As actually worked out, there were probably never more than eight drills working at any one time at the Central Shaft, and this work was entirely suspended in June, 1907, before there was any demand for power in connection with the tunnel lining. The heaviest actual requirement, therefore, was approximately as follows:
(A) Previous to June 25th, 1907:
|
Cubic feet of free air per minute. |
||
| 40 | Drills (22 by 174) | 3,828 |
| 2 | Shovels | 1,600 |
| Pumps and machine-shop, say | 1,000 | |
| 2 | Derricks | 1,000 |
| Total | 7,428 |
(B) After November, 1907 (after completion of enlargement of Central Shaft headings):
|
Cubic feet of free air per minute. |
||
| 32 | Drills (17 by 174) | 2,958 |
| 2 | Shovels | 1,600 |
| Pumps, etc | 1,000 | |
| 3 | Hoisting engines on concrete, each working one-third time | 500 |
| 2 | Derricks | 1,000 |
| Total | 7,058 |
The average number of drillers per shift was about 25 at the two main working faces. There were also from 5 to 10 drills trimming and cleaning up for concrete, say an average of 7, making 32 in all.
After November 1st, it actually required three boilers under steam all the time, and not less than seven compressors running at full capacity, to keep the air at proper pressure, the theoretical capacity
of the compressors being 8,750 cu. ft. of free air per min., as against 7,000 to 7,400 cu. ft., the theoretical maximum requirement.
Some of this deficiency was due to losses in transmission, part also was due to the fact that the actual was probably considerably below the theoretical capacity of the compressors.
[Accidents.]
Two accidents occurred to the powder magazines, the causes of which were never absolutely determined. The first occurred on January 10th, 1907, when the dynamite burned up without exploding. The second accident was on March 3d, 1907, when an explosion occurred which damaged property over a very large area, but did not involve any serious injury to persons, only one man being slightly hurt.
The only serious blasting accident in the tunnels occurred on January 26th, 1908, and was due to a premature blast, the cause for which could not be ascertained.
[Contractor’s Organization.]—The work was in general charge of a superintendent, and, during the time it was being carried on at both ends, an assistant superintendent had charge at night. At each end there was a day and a night walking boss, who had general supervision of the men in the tunnels, the day walking boss being the superior, and responsible for the general conduct of the work at his end, both day and night. Two 10-hour shifts were worked, thirteen shifts every two weeks, no work being done on alternate Sundays and Sunday nights. With the exception of the walking bosses and the master mechanic, all the men changed from the day to the night shift every two weeks.
The organization was approximately as follows, for each shift:
General—Both Tunnels.
| 1 Master mechanic (days only), 1 Machinist, 1 Engine runner, 2 Firemen, 2 Oilers, 1 Electrician and helper, 1 Drill machinist and helper, 3 Blacksmiths and helpers, 1 Powderman, | 1 Walking boss, 4 Locomotive engine runners, 4 Brakemen, 1 Switchman, 1 Foreman on dump, 6 Men on dump, 1 Foreman on track, 6 Men on track. |
In Each Tunnel.
| Drilling and Blasting. | Mucking. | |
| 1 Foreman, 12 Drillers, 12 Helpers, 1 Nipper, 1 Pipe-fitter. | 1 Shovel engineer, 1 Cranesman, 1 Muck boss, 12 Muckers. |
[Records.]
The records of the work have been based largely on the reports of the day and night inspectors, which were made out on regular forms.
A daily report card was made out each morning and forwarded to the office of the chief engineer. It covered the work done for the previous 24 hours, up to 6 o’clock each morning.
A telephone report was made to the resident engineer by the inspectors each day at 8.30 A.M., giving the conditions, number of men, etc., at the opening of the day’s work.
A daily progress profile, on 10 by 10 to the inch cross-section paper, covering the whole length of the tunnels, was kept in the office of the resident engineer. This was mounted in sections, on a piece of composition board, and hung on the wall for convenient reference. The information, showing the progress up to 6 o’clock each morning, was shown on the report of the night inspector, and was plotted on this profile at 7 o’clock each morning. The plotting was left in pencil, and each month’s work was colored in. A progress profile was taken by the men of the alignment corps each Saturday morning and plotted by them, alternate weeks being in red and blue ink on the same profile.
A chart showing the number of drills working, time worked, blasting periods, etc. ([Plate XXIII]), was plotted each morning and was extremely useful, not only in keeping in touch with the work, but in compiling many of the statistics used in the preparation of this paper. These cross-section sheets were ruled 12 by 12 to the inch, thus giving one space per hour horizontally. In the top vertical space are shown the heading drills, their time of stopping and starting, and their number, each heavy line representing one drill. In the next space below are shown the drills on the bench, lift holes, etc.
The blasting time is shown by the portion hatched (shown in red on the original), which covers the whole vertical space when a complete
round of both heading and bench is blasted, and only part, top or bottom, as the case might be, if only one or the other. The number of drillers and muckers at the main working face is shown, and below that (in red ink on the original) the number of cubic yards handled each shift. The time the shovel is working is shown by the heavy line filling a whole space; and the air pressure, platted from the recording gauge charts, is shown in the space below.
A combination daily and weekly report, showing the total number of men working on each section, and the number of cubic yards excavated, was entered every day and kept on a filing board in the office of the resident engineer, and a copy was sent to the main office at the end of the week, with such notes on the back as might be necessary, or of interest.
A report was made out weekly and sent to the contractor’s superintendent, showing any deviations from grade, any tight places, and the station of bench and headings.
A monthly report was made to the chief engineer, giving detailed statistics of the amount of work done, etc., plant installed, and short notes of any matter of interest affecting the work in any way.
[Tunnel Lining.]
[Preliminary Considerations.]—For the placing of the concrete lining, a sub-contract was given to Messrs. King, Rice and Ganey, by Mr. Bradley, which provided substantially that all materials should be supplied by him, and delivered to the sub-contractors at track level, at or near the point in the tunnel at which they were to be placed, and that he would supply light and power; the sub-contractors were to supply the plant, forms, and labor necessary for placing the concrete and water-proofing, building the conduit lines, manholes, etc., etc., to complete the lining, the general form of which is shown on Plate VIII of the paper by Mr. Jacobs, and in [Fig. 10]. The latter also shows the different sections into which the lining was divided for purposes of construction, and the nomenclature adopted for each. It may be noted, incidentally, that the cubic contents of the lining per linear foot of tunnel is almost exactly half the quantity excavated, out to the standard section lines, and as there was some excavation outside of these lines, all of which had to be replaced, the actual quantity of material which had to be brought back into the tunnel
was quite a little more than half the quantity taken out. It will be evident, therefore, that the question of transportation was an important one.
SKETCH SHOWING DIVISION OF LINING FOR PURPOSES OF CONSTRUCTION, AND NAMES OF SECTIONS
An essential part of the agreement with the sub-contractors provided that the operations incident to the placing of the lining should be carried on so as to provide at all times space for a single track of 3-ft. gauge, running through the work, and the necessary clearance for the locomotives and cars used in hauling out the muck. A clearance diagram of one of the “dinkys” used in the tunnels, and its relation to the forms used, is shown by [Fig. 12] and also by [Fig. 16], the 4-yd. Allison cars, used for handling the muck, taking practically the same width, although they were not quite as high. This requirement and the limited space available must be kept in mind in considering the design finally adopted for the forms and plant required in placing
the lining. It should also be kept in mind that, with the rolling stock used, there was only room for a single track through that part of the tunnel where any concrete had been built. As the concrete progressed, therefore, the length of single track was necessarily lengthened, and the problem of transportation was made increasingly difficult.
In working out a design for the bench-wall forms, another highly important and controlling factor, which had to be considered, was the arrangement of the conduit lines, as shown in the general cross-section.[2]
The quantities of the various materials in the lining, per linear foot of tunnel, were as follows:
| Concrete | 7.64 cu. yd. | |
| Rock packing: Paid for | 1.48 cu. yd. | |
| Outside standard section line | 1.74 ” ” | |
| 3.22 ” ” | ||
| Iron and steel | 44.2 lb. | |
| Vitrified conduits | 84.0 duct ft. | |
| Water-proofing | 13.0 sq. ft. | |
| Flags | 3.3 ” ” | |
[General Methods.]—The lining was started at both ends of the tunnels before the headings were finally holed through, so that there was practically a separate organization at each end, each in charge of one of the members of the firm. The work at the Weehawken end was started first, and the plant and scheme of working adopted there was thoroughly tried out before the plant for the western end was built, consequently, the latter was somewhat more efficient, being designed in the light of the experience gained at the Weehawken end.
The general sequence of the plan first adopted in placing the concrete is shown by [Fig. 10]. The concrete was first placed in the foundations up to the elevation of the bottom of the conduit bines, this work, of course, being kept well in advance; next followed, in the order named, the sand-walls, water-proofing, conduits, bench-walls, and finally the arch. The foundation was built in any convenient lengths, multiples of 16 ft., the length of one section of form, the sand-walls in lengths of from 25 to 35 ft., the bench-walls in 25-ft. lengths, and the arch in 10-ft. lengths. Concrete was placed during the day shift only,
the forms being moved partly at night, and partly on the alternate days when concrete was not being placed in them.
Five gangs were organized at each end, the first placed concrete in the foundations in both tunnels, as the excavation was ready. In each tunnel there was a gang which built sand-wall one day and bench-wall the next, the two tunnels alternating so that only one bench-wall was built each day, and finally a gang in each tunnel building arches, a 10-ft. section being completed each day. During the night shift, the arch forms and travelers were moved, and all other forms, etc., were made ready for the concrete to be placed the following day. Some of the conduit laying was done by the night shift, but part of it was necessarily done during the day, as the concrete was built up. A small gang was kept busy in both tunnels, during the day shift, laying conduits and water-proofing. The latter two operations were generally performed by the same gang.
This organization, of course, required considerable regularity in the work, and this was finally attained, but at the beginning many sections were often not finished on time, thus creating considerable confusion. The progress possible with this organization (finally maintained with great regularity) was 75 ft. of bench-wall and 60 ft. of arch per week at each of the two working faces in each tunnel. This allowed the bench-wall to gain considerably on the arch, and therefore at a suitable point, as shown on the progress diagram, [Fig. 9], a third pair of arches was started, one in each tunnel, increasing the progress on the arches to 180 ft. per week in each tunnel.
[Mixing and Transportation.]—All the concrete used on this section was mixed in Hains mixers, one being at each end. At the Weehawken shaft the mixer was installed in the framework supporting the head-house and elevators; and storage bins were arranged above, as shown by [Fig. 11], A, the whole structure being somewhat strengthened to allow this to be done. At the western end the mixer was placed immediately under the bins of the stone crusher, as shown by Fig. 11, B, the track below being connected directly with the tunnels. The stone bin under the screen of the crusher plant at the Hackensack end was divided into three parts, the center being filled with sand by a derrick having a clam-shell bucket, the other two with stone directly from the screen above.
[Cross-Section of Hains Mixer Installation, at Weehawken Shaft]
(Larger view)
[Cross-Section of Hains Mixer Installation, Stone and Sand Bins Above and Screen of Crusher, at Hackensack Portal]
(Larger view)